A meta-analysis of critical causes of project delay using Spearman’s rank and relative importance index integrated approach

Author:

Amarkhil Qais11,Elwakil Emad11,Hubbard Bryan11

Affiliation:

1. School of Construction Management, Purdue University, West Lafayette, IN 47907, USA.

Abstract

This meta-analysis has examined the past ten years’ studies concerning the causes of construction project delay. It aims to update the subject area and investigate critical causes of project delay in three different conditions of the external environment. The data from 50 studies have been analyzed and synthesized to determine the top ten critical causes of delay. The Relative Importance Index (RII) technique was applied to rank the critical causes; subsequently, the Spearman’s rank correlation coefficient was calculated to evaluate the critical causes. The review findings indicate substantial differences between the critical causes of project delay in defined situations. The top ten critical causes of delay in developed countries root in the project’s internal environment. The leading causes of delays in developing countries are from the project’s internal and task environment. While in countries with various constraints and high risk, the general environment has a critical impact alongside the project task and internal environment on time overrun of a project. Moreover, this review summarized and categorized the best available studies to propose a systematic approach in identifying critical causes of delay to bridge the existing knowledge gap.

Publisher

Canadian Science Publishing

Subject

General Environmental Science,Civil and Structural Engineering

Reference64 articles.

1. Aggregation of factors causing cost overruns and time delays in large public construction projects

2. The professionals’ perspective on the causes of project delay in the construction industry

3. Al-Ghafly, M.A. 1995. Delay in the construction of public utility projects in Saudi Arabia. Master’s thesis, Construction Engineering and Management Department, King Fahd University of Petroleum and Minerals.

4. Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3