Abstract
Purpose
The purpose of this paper is to explore the impact that cost overruns and time delays exert on large public construction projects to clarify how past and current research regard factors causing cost overruns and time delays in large public construction projects.
Design/methodology/approach
This paper, which is based on an analysis of a literature selection consisting of 40 journal articles, investigates and ranks the occurrence of and the explanations for cost overruns and time delays in large public construction projects. The study makes use of a kiviat diagram/radar chart in order to visualize multivariate data.
Findings
Aggregated rankings of important causes of cost overruns and time delays are reported. These show a strong emphasis on the management aspect as a primary cause of cost overruns and delays. Additionally, there seems to be a trend toward deemphasizing the role of financial considerations in explaining cost overruns and delays. It is argued that there needs to be a more rigorous assessment of the impact that each factor has on cost increases and delays based on factual observed data as opposed to retrospective accounts from questionnaire respondents.
Research limitations/implications
Only public construction projects have been considered. The results will not be directly applicable to privately funded construction projects and/or projects of a smaller size.
Originality/value
The use of trend data, as illustrated in a kiviat diagram, showing how different ranking factors causing cost overruns and time delays has changed in importance over time.
Subject
General Business, Management and Accounting,Building and Construction,Architecture,Civil and Structural Engineering
Reference36 articles.
1. Risk management in the construction industry using combined fuzzy FMEA and Fuzzy AHP;Journal of Construction Engineering Management,2010
2. Adam, A., Josephson, P.E. and Lindahl, G. (2015), “Implications of cost overruns and time delays on major public construction projects”, in Shen, L., Ye, K. and Mao, C. (Eds), Proceedings of the 19th International Symposium on Advancement of Construction Management and Real Estate, Springer, Berlin and Heidelberg, pp. 747-758.
3. Factors affecting contractors’ risk of cost overburden;Journal of Management in Engineering,1998
4. Empirical assessment of the likelihood and duration of highway project time delays;Journal of Construction Engineering Management,2012
Cited by
91 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献