Improving Design Quality by Contractor Involvement: An Empirical Study on Effects

Author:

Lappalainen EelonORCID,Uusitalo Petteri,Pikas ErgoORCID,Seppänen OlliORCID,Peltokorpi AnttiORCID,Uusitalo PetriORCID,Reinbold Ana,Menzhinskii Nikolai

Abstract

It is generally acknowledged that good-quality design is a prerequisite for good quality and productive construction work. One proposed measure to improve the quality of construction has been contractors’ involvement in the design phase, and this phenomenon has been studied by several researchers. However, such approaches have not adequately addressed how this involvement affects the quality of the design. In this study, the aim was to study the effects of the early involvement of contactors on design quality based on evaluating the design quality factors. A case study was used to collect data and content analysis to analyze structural drawings and design meeting minutes of a large-scale infrastructure project. Particularly, the focus was on gathering information on the quality of the design and how it was addressed in the design coordination. We combined this quantitative data with qualitative open-ended thematic interviews, including respondents who led and coordinated the design on both the client and contractor sides. Our findings suggest that despite the vast amount of design changes, contractors’ involvement and development work in the detailed design phase improved design quality and constructability. Our findings also suggest that the contractor’s involvement during the schematic design phase had a design-enhancing effect in the detailed design phase. This study contributes to our understanding of contractors’ valuable role in design quality.

Publisher

MDPI AG

Subject

Building and Construction,Civil and Structural Engineering,Architecture

Reference68 articles.

1. Total quality management in the construction process

2. The Construction (Design and Management) Regulations, 1994: Explained;Joyce,2001

3. Reliability and Stability Buffering Approach in Concurrent Design and Construction Projects;Lee;Proceedings of the 11th Annual Conference of the International Group for Lean Construction,2003

4. Lean Design Management: A New Paradigm for Managing the Design and Documentation Process to Improve Quality?;Tilley;Proceedings of the 13th Annual Conference of the International Group for Lean Construction,2005

5. Early Contractor Involvement in Design and Its Impact on Construction Schedule Performance

Cited by 1 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3