Artificial Neural Network Model to Predict Final Construction Contract Duration

Author:

Alsugair Abdullah M.1ORCID,Al-Gahtani Khalid S.1ORCID,Alsanabani Naif M.1ORCID,Alabduljabbar Abdulmajeed A.1,Almohsen Abdulmohsen S.1ORCID

Affiliation:

1. Department of Civil Engineering, King Saud University, P.O. Box 2454, Riyadh 114, Saudi Arabia

Abstract

Forecasting the final construction contract duration at an early stage plays a vital role in the progress of a project. An inaccurate project duration prediction may lead to the project’s benefits being lost. It is essential to precisely predict the duration due to the presence of several different factors. This paper contributed to developing a model to predict final construction contract duration (FCCD) in the early stages based on parameters characterized as few and shared for any contract. (contract cost, contract duration, and sector). This paper developed an Artificial Neural Network (ANN) model based on 135 Saudi construction project data. The development model has three stages. The first stage was standardization and augmentation using Zavadskas and Turskis’ logarithmic and Pasini methods. The second and third stages were the first and second analyses of the ANN models, respectively. The first analysis aimed to promote the used data and integrate them into the second analysis to develop the ANN model. The ANN models were compared with three linear regression (LR) models (LR1, LR2, and LR3) and other models in the literature. The results revealed that the accuracy of the ANN model provides reasonable accuracy with an average mean absolute percentage error (MAPE) of 12.22%, which is lower than the LR3′s MAPE by 27.03%. The accuracy of the ANN model is similar to that of earned value management (EVM) in the previous study. This paper supports research to deal with relatively little data and integrate them into a neural network. The ANN model assists the stakeholder in making appropriate decisions for the project during the pre-tendering phase by predicting the actual contract duration based on the CC, CD, and project sector.

Funder

Deputyship for Research and Innovation, Ministry of Education in Saudi Arabia

Publisher

MDPI AG

Subject

Fluid Flow and Transfer Processes,Computer Science Applications,Process Chemistry and Technology,General Engineering,Instrumentation,General Materials Science

Reference39 articles.

1. Bertelsen, S., and Sacks, R. (2007, January 18–20). Towards a new understanding of the construction industry and the nature of its production. Proceedings of the 15th Conference of the International Group for Lean Construction, East Lansing, MI, USA.

2. Impact of construction delay controlling parameters on project schedule: DEMATEL-System dynamics modelling approach;Ajayi;Front. Built Environ.,2022

3. Tafazzoli, M., and Shrestha, P.P. (2017, January 5–8). Investigating Causes of Delay in US Construction Projects. Proceedings of the 53rd ASC Annual International Conference, Seattle, WA, USA.

4. Analysis of Delay Impact on Construction Project Based on RII and Correlation Coefficient: Empirical Study;Gebrehiwet;Procedia Eng.,2017

5. Khattri, T., Agarwal, S., Gupta, V., and Pandey, M. (2016). Causes and Effects of Delay in Construction Project. Int. Res. J. Eng. Technol., Available online: www.irjet.net.

Cited by 7 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3