Abstract
Purpose
This paper aims to explore the relationship between delay factors and construction project performance with respect to project risk mitigation strategies as moderators.
Design/methodology/approach
Random sampling was used to select the sample of the study. Data were gathered through a survey of 204 Malaysian construction companies. The data were analysed using the partial least squares technique.
Findings
The results indicate that environmental, resource and coordination issues negatively affect construction project performance. Project visibility and flexibility can mitigate the negative effects of both resource and coordination issues on project performance. Furthermore, supplier development can mitigate the negative effects of coordination issues.
Practical implications
The findings of the study will be useful for construction firms to complete construction projects timely, within a scheduled budget and with only minor defects if adopted.
Originality/value
This study is among the first to empirically test the moderating role of risk mitigation strategies on the relationship between delay factors and project performance in the construction industry.
Reference91 articles.
1. Causes of delay in building construction projects in Egypt;Journal of Construction Engineering and Management,2008
2. Barriers to green innovation initiatives among manufacturers: the Malaysian case;Review of Managerial Science,2016
3. Delays in construction: a brief study of the Florida construction industry,2003
4. The effects of construction delays on project delivery in Nigerian construction industry;International Journal of Project Management,2002
5. Risk analysis and management in construction;International Journal of Project Management,1997
Cited by
30 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献