Abstract
Purpose
The purpose of this paper is to identify the main reworks and their causes in a case study of the ongoing mass housing project in Iran. Using the real data captured from the project, the most important causes for reworks have been computed and prioritized.
Design/methodology/approach
More than 900 non-conformance forms filled in the construction site have been used to categorize reworks. Then, the frequency and cost of each rework group in the project have been estimated. Finally, using these data, the primary classification and sorting of the main causes of reworks have been specified.
Findings
Results show “Poor site supervision and inspection” with 24 percent of costs had the most impact and “unclear project management process” with about 6 percent of costs had the least impact on the formation of non-conformances. “Cost of each incidence” (COI) ranged from 0.67 for “The need to categorize the complicated operations” to 1.86 for “Unclear project management process.”
Research limitations/implications
The causes of rework which are not in contractor’s hand (like change orders from the client) have not been considered in this study.
Originality/value
Although some works have been done in rework causes, the key elements and causes of reworks in mass housing projects in developing countries have not been yet fully specified through the real data. Knowing the root causes of reworks can help project managers to remove them and reduce reworks costs in future projects. COI which is defined here for the first time and computed in a relative concept could be a good criterion to compare rework causes between two or more similar projects.
Subject
Strategy and Management,General Business, Management and Accounting
Reference34 articles.
1. The cost of non-conformance during a highway project: a case study;Construction Management and Economics,1995
2. Effect of quality supervision on rework in the Indonesian context;Asia Pacific Building and Construction Management Journal,2001
3. Quality failure costs in civil engineering projects;International Journal of Quality & Reliability Management,2000
4. Causes of quality deviations in design and construction;Journal of Construction Engineering and Management,1992
Cited by
16 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献