Variations in Building Construction Projects in Ghana: A Public Organisational Perspective

Author:

Akomah Benjamin Boahene1,Mustapha Zakari1,Mensah Justice William2,Lawson Roland William3

Affiliation:

1. Department of Building Technology , Cape Coast Technical University (CCTU) , Cape Coast , Ghana

2. 3 Public Works Department , Cape Coast , Ghana

3. 4 Directorate of Physical Development and Estate Management , University of Cape Coast (UCC) , Cape Coast , Ghana

Abstract

Abstract The occurrence of variations in building construction contracts is a subject that needs some attention in public sector projects. They are, almost all the time, detrimental rather than beneficial variations. The paper aimed to identify the nature of variations in government-initiated building projects over fourteen years, from 2000 to 2014, in the Central Region and their impacts. Preliminary counts of documents revealed that a total of 348 projects were executed over the period. The data collection process started by first sorting out files, contract documents, and payment certificates for the period under consideration. These documents were scrutinised one after the other to detect possible variations. The inclusion criterion for selecting a project was if a project had any form of variation(s) recorded. After thoroughly examining these 348 project documents, 84 were found to have variations. The study identified additional works and substitutions as the most inherent variations in public building projects in the Central Region. About 85 % of the variations found in the 84 projects with various forms of variations were additional works and substitutions. It was revealed that the cost of multiple variations was higher than single variations. Projects with multiple variations had high percentage variation and durations than others. Percentage variation in some instances was 400 %. The study identified that multiple variations were more costly than single variations. The highest variation cost identified was (USD 211 864.41 or EUR 183 150.18) for one project. The study identified the nature of variations that usually occurred in government building projects and their association with both cost and time. The study asserts that the presence of multiple change orders has substantial financial significance and should be diligently avoided through efficient project initiation and planning.

Publisher

Walter de Gruyter GmbH

Subject

General Earth and Planetary Sciences,General Engineering,General Environmental Science

Reference54 articles.

1. Adedokun, O., & Egbelakin, T. (2022). Structural equation modelling of risk factors influencing the success of building projects. Journal of Facilities Management, 1472–5967. https://doi.org/10.1108/JFM-01-2022-0002

2. Ajayi, B. O., & Chinda, T. (2022). Impact of construction delay-controlling parameters on project schedule: DEMATEL-system dynamics modeling approach. Frontiers in Built Environment, 8, Article 799314. https://doi.org/10.3389/fbuil.2022.799314

3. Akomah, B. B., Mustapha, Z., & Mensah, J. W. (2018). Cost impacts of variations on building construction projects. MOJ Civil Engineering, 4(5), 386–392. https://doi.org/10.15406/mojce.2018.04.00133

4. Akomah, B. B., Zakari, M., & Enoch Ayeh, E. (2020a). Impact of cost of construction projects in Cape Coast metropolis. Buletinul Institutului Politehnic Din Iaşi, 66(1), 95–112.

5. Akomah, B. B., Mustapha, Z., & Ofosu, E. K. (2020b). Contractors’ commitment to early completion of projects. Australian Journal of Science & Technology, 4(2), 283–288. https://www.researchgate.net/publication/343008004_Contractors’_commitment_to_early_completion_of_projects

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3