Simulation-Optimization for the Planning of Off-Site Construction Projects: A Comparative Study of Recent Swarm Intelligence Metaheuristics

Author:

Hussein MohamedORCID,Eltoukhy Abdelrahman E. E.ORCID,Darko AmosORCID,Eltawil Amr

Abstract

Off-site construction is a modern construction method that brings many sustainability merits to the built environment. However, the sub-optimal planning decisions (e.g., resource allocation, logistics and overtime planning decisions) of off-site construction projects can easily wipe away their sustainability merits. Therefore, simulation modelling—an efficient tool to consider the complexity and uncertainty of these projects—is integrated with metaheuristics, developing a simulation-optimization model to find the best possible planning decisions. Recent swarm intelligence metaheuristics have been used to solve various complex optimization problems. However, their potential for solving the simulation-optimization problems of construction projects has not been investigated. This research contributes by investigating the status-quo of simulation-optimization models in the construction field and comparing the performance of five recent swarm intelligence metaheuristics to solve the stochastic time–cost trade-off problem with the aid of parallel computing and a variance reduction technique to reduce the computation time. These five metaheuristics include the firefly algorithm, grey wolf optimization, the whale optimization algorithm, the salp swarm algorithm, and one improved version of the well-known bat algorithm. The literature analysis of the simulation-optimization models in the construction field shows that: (1) discrete-event simulation is the most-used simulation method in these models, (2) most studies applied genetic algorithms, and (3) very few studies used computation time reduction techniques, although the simulation-optimization models are computationally expensive. The five selected swarm intelligence metaheuristics were applied to a case study of a bridge deck construction project using the off-site construction method. The results further show that grey wolf optimization and the improved bat algorithm are superior to the firefly, whale optimization, and salp swarm algorithms in terms of the obtained solutions’ quality and convergence behaviour. Finally, the use of parallel computing and a variance reduction technique reduces the average computation time of the simulation-optimization models by about 87.0%. This study is a step towards the optimum planning of off-site construction projects in order to maintain their sustainability advantages.

Funder

The Egyptian Ministry of Higher Education (MOHE) grant and the Japanese International Cooperation Agency (JICA) in the scope of the Egypt-Japan University of Science and Technology

Publisher

MDPI AG

Subject

Management, Monitoring, Policy and Law,Renewable Energy, Sustainability and the Environment,Geography, Planning and Development

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3