Expert Opinion on the Key Influencing Factors of Cost Control for Water Engineering Contractors
-
Published:2023-04-20
Issue:8
Volume:15
Page:6963
-
ISSN:2071-1050
-
Container-title:Sustainability
-
language:en
-
Short-container-title:Sustainability
Author:
Ding Zhenhan1,
Liu Xun1ORCID,
Xue Zhiyuan1,
Li Xiaobo1
Affiliation:
1. School of Civil Engineering, Suzhou University of Science and Technology, No. 1 Kerui Rd, New District, Suzhou 215000, China
Abstract
There are many unpredictable circumstances during the implementation process of a water conservancy project, which often cause financial loss, increased construction costs and schedule delays. This paper investigates the influence factors for water conservancy project cost control. The present study used the factor analysis method to extract the major cost control influence factors, and performed a correlation analysis to clarify the relationship between these cost control influence factors and the sub-factors under each factor. Several water conservancy project practitioners were invited to analyze the sub-factors of the cost control influence factors and to provide some strategic suggestions in terms of minimizing the impact of the influence factors. The results of the study illustrate that in construction, water engineering contractors who want to reduce costs need to focus on the lack of a clear definition for the scope of works, subcontractors’ insufficient ability to perform the work, site construction conditions and the escalation of the construction material cost. The correlation analysis demonstrated that unreasonable requirements from the supervision unit and unfair standpoints of the supervision unit are highly correlated; the insufficient mobilization ability and lack of management capability of the subcontractor are medium correlated; the site construction conditions and the lack of a clear definition for the scope of works are medium correlated; and the escalation of the construction material cost and shortage of construction materials are medium correlated. This facilitates future water works contractors to identify the underlying causes of cost increases.
Funder
Philosophy and Social Science Research in Colleges and Universities in Jiangsu Province
Fundamental Research Funds for the Central Universities
Jiangsu Provincial Construction System Science and Technology Project of Housing and Urban and Rural Development Department
Postgraduate Research and Practice Innovation Program of Jiangsu Province
Subject
Management, Monitoring, Policy and Law,Renewable Energy, Sustainability and the Environment,Geography, Planning and Development,Building and Construction
Reference53 articles.
1. Assessing the Impact of Cost Overrun Causes in Transmission Lines Construction Projects;Pham;Ksce J. Civ. Eng.,2020
2. The progress and trend of BIM research: A bibliometrics-based visualization analysis;Wen;Autom. Constr.,2021
3. Cost Management and Forecasting Method for the Whole Life Cycle of Water Conservancy Projects Based on Multiple Regression Analysis;Li;Sci. Program.,2022
4. Bin Seddeeq, A., Assaf, S., Abdallah, A., and Hassanain, M.A. (2019). Time and Cost Overrun in the Saudi Arabian Oil and Gas Construction Industry. Buildings, 9.
5. Predicting Cost Escalation Pathways and Deviation Severities of Infrastructure Projects Using Risk-Based Econometric Models and Monte Carlo Simulation;Bhargava;Comput. Aided Civ. Infrastruct. Eng.,2017
Cited by
2 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献