Affiliation:
1. Key Laboratory of In-Situ Property-Improving Mining of Ministry of Education, Taiyuan University of Technology, Taiyuan 030024, China
2. College of Mechanical and Vehicle Engineering, Taiyuan University of Technology, Taiyuan 030024, China
Abstract
Gob-side entry retaining by roof cutting, a pillarless mining technique, plays a critical role in maintaining continuous production, rapid connection, and enhancing the coal recovery rate in fully mechanized top coal caving working faces. This technique stands as a sustainable development method in coal mining. The present research, set against the backdrop of the Yitang Coal Mine 100602 top coal gob-side entry retaining by roof cutting, investigates the influence of roof-cutting borehole depth, borehole dip angle, mining height, and coal seam thickness on stability in an ultra-thick coal seam under 12 distinct mining conditions. A typical model of overburden structure post-roof pre-splitting was established to study the failure mechanism of the top coal roof. The results reveal that the dip angle and depth of the roof pre-fracturing borehole significantly impact the movement characteristics of the overlying strata. Optimal conditions are found when the dip angle and depth of the roof pre-fracturing borehole, the mining height, and the top coal thickness are 10°, 16 m, 4 m, and 4 m, respectively. Under these circumstances, the load transfer from the goaf to the gob-side entry can be effectively intercepted, mitigating the influence of roof fracture activities on the top coal gob-side entry. Field measurements confirm that suitable anchor-net support can stabilize the roof’s rock structure. This research underpins the significance of roof pre-fracturing for the promotion and application of top coal gob-side entry retaining by roof cutting in ultra-thick coal seams.
Funder
National Natural Science Foundation of China
Natural Science Foundation of Shanxi Province
Scientific Research Grant Project for Returned Overseas Students in Shanxi Province
Teaching Reform Innovation Project for Higher Education Institutions in Shanxi Province
China Postdoctoral Science Foundation funding project
Subject
Energy (miscellaneous),Energy Engineering and Power Technology,Renewable Energy, Sustainability and the Environment,Electrical and Electronic Engineering,Control and Optimization,Engineering (miscellaneous),Building and Construction
Reference38 articles.
1. Wang, K., Huang, Y., Gao, H., Zhai, W., Qiao, Y., Li, J., Ouyang, S., and Li, W. (2020). Recovery Technology of Bottom Coal in the Gob-Side Entry of Thick Coal Seam Based on Floor Heave Induced by Narrow Coal Pillar. Energies, 13.
2. Study on the mechanism of a new fully mechanical mining method for extremely thick coal seam;Lv;Int. J. Rock Mech. Min. Sci.,2021
3. Rupture and Migration Law of Disturbed Overburden during Slicing Mining of Steeply Dipping Thick Coal Seam;Liu;Adv. Civ. Eng.,2020
4. Floor Pressure-Relief During Top Slice Mining of Extra-Thick Coal Seams and Its Implications for Gas Drainage Application;Liu;Geotech. Geol. Eng.,2019
5. Comparison of rockburst occurrence during extraction of thick coal seams using top-coal caving versus slicing mining methods;Li;Can. Geotech. J.,2018
Cited by
3 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献