Stability Analysis of Downstream Dam Expansion Tailings Pond

Author:

Jin Jiaxu1,Zhang Hongyue1ORCID,Xu Liang2,Zhou Kelin1,Lv Xiangfeng3

Affiliation:

1. Liaoning Technology University, Fuxin 123000, China

2. Qingdao University of Technology, Qingdao 266000, China

3. School of Civil and Resource Engineering, University of Science and Technology Beijing, Beijing 100083, China

Abstract

The buildup of tailings in China has expanded dramatically with economic development and industrial demand, and the safety of tailings reservoirs has become increasingly serious. Due to the difficulty in finding a new reservoir site, the expansion approach of building a new tailings dam downstream of the original reservoir area was investigated. The stability of the tailings reservoir after expansion was calculated using the traditional dynamic and static stability solution method and taking into account the unpredictability of dam construction materials and tailings material parameters in the reservoir area. The results reveal that throughout the tailings accumulation process in the new reservoir, the tailings will build a back pressure slope at the original reservoir’s initial dam, which can considerably improve the original reservoir’s dynamic and static stability. The Monte Carlo method clearly outperforms older methods for tailing pond stability analysis. The results of this paper’s calculations will give a theoretical foundation and practical reference for the later management and maintenance of such tailings reservoirs, as well as fresh ideas and insights for comparable projects due to limited site selection.

Publisher

Hindawi Limited

Subject

Civil and Structural Engineering

Reference38 articles.

1. A global-scale spatial assessment and geodatabase of mine areas;T. Liang;Global and Planetary Change,2021

2. Floods from tailings dam failures;M. Rico;Journal of Hazardous Materials,2008

3. Formation and evolution characteristics of dam breach and tailings flow from dam failure: an experimental study;S. Tian;Natural Hazards,2021

4. Experimental study of similar simulation of tailings dam-break[J];G. Z. Yin;Chinese Journal of Rock Mechanics and Engineering,2010

5. Severe impacts of the brumadinho dam failure (minas gerais, Brazil) on the water quality of the paraopeba river;F. Thompson;The Science of the Total Environment,2020

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3