Quantifying Schedule Delay Risk in Construction Projects: A Data-Driven Approach with BIM and Probabilistic Reliability Analysis

Author:

Zhang Shen1ORCID,Wang Xingyu1ORCID

Affiliation:

1. Central-South Architectural Design Institute Co., Ltd., Wuhan 430071, China

Abstract

Progress management is an important scheme of construction management. In practical affairs, many unknown factors may lead to potential project delays and make the schedule risky. To address this issue, this paper proposes a data-driven construction progress evaluation method that employs a probabilistic reliability analysis with BIM to effectively quantify the risk of schedule delay. By identifying critical tasks and probable failure conditions in uncertain environments, this method enables project managers to take proactive measures to keep their projects on schedule. Through our case study, we have demonstrated that the proposed method is highly effective in dynamically evaluating the project progress with both accuracy and efficiency. Besides, this system offers a more efficient way for managers to gather information, evaluate progress, and identify critical tasks, and provides project managers with a data-driven understanding of the risks and uncertainties related to project schedules, enabling them to take proactive measures to minimize the potential delays and ensure successful project delivery.

Funder

Ministry of Housing and Urban-Rural Development

Publisher

Hindawi Limited

Subject

Civil and Structural Engineering

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3