Abstract

Because of the surrounding environment restriction, some sections of the Lanzhou Metro Line 2 were forced to change the original open excavation method to the concealed excavation method. Among them, the ingate is the transitional section connecting the shaft and the cross passage, which is accompanied by the force conversion of the structure during the plan change process, and accidents are prone to occur. Combining this project situation, a construction scheme for turning the shaft from the cross passage into the ingate of mine line was proposed, and the finite element software is used to simulate the scheme. Numerical analysis shows that the stability of the tunnel supporting structure, shaft, and cross passage all meet the design requirements. The final ground settlement caused by the proposed construction method is 7.1 mm, and the settlement of the vault is 11.97 mm. It also turns out that the proposed construction method causes less deformation, and the method can be applied to the construction of the ingate conversion. The rationality of the method and numerical model was further verified by the comparison between the monitored data of surface settlement and vault sinking and numerical simulation results. Finally, the modified concealed excavation method and the original open excavation construction method is compared. It is concluded that the concealed excavation method is superior to the original open excavation method in terms of construction schedule, construction safety, economic benefits, and impact of construction on the surrounding environment. It indicates that it is a good choice to replace the construction method early if necessary. The successful implementation of this project can provide a reference for the design and implementation of similar urban subway projects.

Funder

National Natural Science Foundation of China

Publisher

Hindawi Limited

Subject

Civil and Structural Engineering

Reference24 articles.

1. Case Study of the Effect of Rainfall Infiltration on a Tunnel Underlying the Roadbed Slope with Weak Inter-Layer

2. Design and construction of enlarging shield tunnel sections of large dimensional shield tunnels for the non-open-cut method

3. Control points of supervision in subway station constructed with open-cut method;J. Soetjahjo;Municipal Engineering Technology,2010

4. A Numerical Study on Parameters Affecting Seismic Behavior of Cut and Cover Tunnel

5. Technology for construction of multi-arch tunnels with twin large spans and shallow embedment and concealed excavation beneath existing railway;H. Jinyin;Value Engineering,2012

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3