Completing road construction projects in time is a challenge for developing countries, specifically for Tanzania, where great economic costs result from difficulties in identifying and reducing the factors that cause the delay.
Methods
This study addresses factors that cause the delay of a road construction project in Tanzania and proposes some methods that could potentially reduce this delay. A structured questionnaire was drawn up through an interactive online workshop with the help of experts and professionals from the road construction sector in Tanzania, and follow-up interviews were conducted.
Results and Discussion
In addition, the first results were analyzed, and the factors identified were combined into five important groups, namely, client-related, consultant-related, contractor-related, design-related, and external factors. These were the main contributing aspects to delays in road construction projects in Tanzania.
Conclusion
Furthermore, from across these groups, six significant causes of delays emerged, and these were inadequate access to finance and delayed payments for completed work, financial problems or difficulties, unwillingness or inability to sustain operations over long periods of non-payment, an unrealistic program of works (Works Schedule), inadequate site management, and political interference.
Publisher
Bentham Science Publishers Ltd.
Subject
Transportation,Modeling and Simulation
Reference25 articles.
1. Enshassi A, Al-Najjar J, Kumaraswamy M.
Delays and cost overruns in the construction projects in the Gaza Strip.
J Finan Manag Property Construc
2009;
14
(2)
: 126-51.
2. Liebing PW.
Liebing, “The construction industry: processes, players, and practices,” p. 205, 2000, [Accessed: Nov. 30, 2021]. [Online]. Available: https://books.google.com/books/about/The_Construction_Industry.html?id=LWseAQAAIAAJ
3. Kaliba C, Muya M, Mumba K.
Cost escalation and schedule delays in road construction projects in Zambia.
Int J Proj Manag
2009;
27
(5)
: 522-31.
4. F. NEGA.
Causes and effects of cost overrun on public building construction projects in ethiopia In partial fulfillment o A Thesis Submitted to the School of Graduate Studies of
2008.
5. Talukhaba AA.
An investigation into factors causing construction project delays in Kenya
1999.