An Analysis of the Main Causes of Delays in the Completion of Road Construction Projects: A Case Study of Tanzania

Author:

Kullaya Donati Michael,Alemu Muluken Kassahun,Yeom Chun Ho

Abstract

Introduction Completing road construction projects in time is a challenge for developing countries, specifically for Tanzania, where great economic costs result from difficulties in identifying and reducing the factors that cause the delay. Methods This study addresses factors that cause the delay of a road construction project in Tanzania and proposes some methods that could potentially reduce this delay. A structured questionnaire was drawn up through an interactive online workshop with the help of experts and professionals from the road construction sector in Tanzania, and follow-up interviews were conducted. Results and Discussion In addition, the first results were analyzed, and the factors identified were combined into five important groups, namely, client-related, consultant-related, contractor-related, design-related, and external factors. These were the main contributing aspects to delays in road construction projects in Tanzania. Conclusion Furthermore, from across these groups, six significant causes of delays emerged, and these were inadequate access to finance and delayed payments for completed work, financial problems or difficulties, unwillingness or inability to sustain operations over long periods of non-payment, an unrealistic program of works (Works Schedule), inadequate site management, and political interference.

Publisher

Bentham Science Publishers Ltd.

Subject

Transportation,Modeling and Simulation

Reference25 articles.

1. Enshassi A, Al-Najjar J, Kumaraswamy M. Delays and cost overruns in the construction projects in the Gaza Strip. J Finan Manag Property Construc 2009; 14 (2) : 126-51.

2. Liebing PW. Liebing, “The construction industry: processes, players, and practices,” p. 205, 2000, [Accessed: Nov. 30, 2021]. [Online]. Available: https://books.google.com/books/about/The_Construction_Industry.html?id=LWseAQAAIAAJ

3. Kaliba C, Muya M, Mumba K. Cost escalation and schedule delays in road construction projects in Zambia. Int J Proj Manag 2009; 27 (5) : 522-31.

4. F. NEGA. Causes and effects of cost overrun on public building construction projects in ethiopia In partial fulfillment o A Thesis Submitted to the School of Graduate Studies of 2008.

5. Talukhaba AA. An investigation into factors causing construction project delays in Kenya 1999.

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3