Delays and cost overruns in the construction projects in the Gaza Strip
Author:
Enshassi Adnan,Al‐Najjar Jomah,Kumaraswamy Mohan
Abstract
PurposeDelays and cost overruns are evidently frequent problems in the construction industries of many developed and developing countries. The purpose of this paper is to assess factors leading to time overruns (delays) and cost overruns in construction projects in the Gaza Strip. Since there appear to be additional special contributors to delays here, the relative perceptions of contractors, consultants and owners are compared, based on a listing of causal factors derived from previous studies elsewhere, together with other factors arising from special conditions in the Gaza Strip.Design/methodology/approachA survey of a randomly selected samples yielded responses from 66 contractors, 27 consultants, and 31 owners. The survey included 110 delay factors/causes which were grouped into 12 major groups. The same survey also included 42 cost overrun factors. The level of importance of the delays and cost overrun factors were measured and ranked by their importance indexes, according to the perspectives of contractors, consultants, and owners.FindingsThere seems to be a general agreement between contractors, consultants and owners regarding causes of delays and cost overruns. The main four causes of time delays included strikes and border closures, material‐related factors, lack of materials in markets, and delays in materials delivery to the site. Additionally, the main three causes for cost overruns included price fluctuations of construction materials, contractor delays in material and equipment delivery, and inflation.Originality/valueThe outcome of this paper will assist owners, contractors, and consultants in understanding the reasons for delays and cost overruns, thus eliminating or minimizing these causes. This could be achieved by better management of the projects and by finding new methods for storing the critical materials from the beginning of the project. Furthermore, the local government is advised to initiate legislation to overcome problems arising from monopolies in the supply of construction materials.
Subject
Economics and Econometrics,Finance,Accounting,Business and International Management
Reference40 articles.
1. Abdul‐Rahman, H., Yahya, I., Berawi, A. and Wah, L.W. (2008), “Conceptual delay mitigation model using a project learning approach in practice”, Construction Management and Economics, Vol. 26, pp. 15‐27. 2. Abdul‐Rahman, H., Berawi, A., Mohamed, O., Othman, M. and Yahya, I. (2006), “Delay mitigation in the Malaysian construction industry”, Journal of Construction Engineering and Management, Vol. 132 No. 2, pp. 125‐33. 3. Ahmed, S.M., Azhar, S., Kappagantula, P. and Gollapudi, D. (2003), “Delays in construction: a brief study of the Florida construction industry”, Proceedings of the 39th Annual Conference of the Associated Schools of Construction, Clemson University, Clemson, SC (final report, Miami, FL). 4. Aibinu, A.A. and Jagboro, G.O. (2002), “The effects of construction delays on project delivery in Nigerian construction industry”, International Journal of Project Management, Vol. 20 No. 8, pp. 593‐9. 5. Alaghbari, M.W., Khadir, M.R.A., Salim, A. and Emawati, . (2007), “The significant factors causing delay of building construction projects in Malaysia”, Journal of Engineering, Construction and Architectural Management, Vol. 14 No. 2, 8, pp. 192‐206, 8.
Cited by
163 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献
|
|