HOW TO GET INTERNATIONAL CONSTRUCTION PROJECTS DELIVERED ON TIME: FROM CHINESE CONTRACTORS’ PERSPECTIVE

Author:

Sun Hongxin1,Tang Wenzhe1,Duffield Colin F.2,Zhang Lihai2,Hui Felix Kin Peng2

Affiliation:

1. Tsinghua University, Institute of Project Management and Construction Technology, State Key Laboratory of Hydroscience and Engineering, New Hydraulic Building, 100084 Beijing, China

2. Department of Infrastructure Engineering, The University of Melbourne, Victoria 3010, Australia

Abstract

67.9% of Chinese international construction projects are seriously delayed, which creates the potential for instability in its rapidly growing share of global contracting markets. A greater understanding of the reasons behind the challenges confronting international contractors is urgently required such that improvements can be developed that ultimately will benefit many countries. This study aims to investigate the time performance of international projects in developing countries and to explore the root causes of time overrun. Based on both quantitative and qualitative analysis of 112 case study projects, collected from 12 of the largest Chinse state-owned enterprises (SOEs), this study identifies the distinctive characteristics of three types of projects (late, acceptable, early) classified based on their time performances. It is established that time performance is significantly related to the contractor’s adaptability and project complexity. The results reveal the root causes of construction delays in international project delivery, which provides a structured and in-depth understanding of both internal and external time performance influential factors. The above findings provide sound basis for guiding practitioners in choosing appropriate strategies to improve project time performance, such as encouraging cross-cultural dialogues, integrating global resources and establishing long-term global partnerships with stakeholders.

Publisher

Vilnius Gediminas Technical University

Subject

Strategy and Management,Civil and Structural Engineering

Reference77 articles.

1. Causes of Delay in Building Construction Projects in Egypt

2. Factorial Causative Assesments and Effects of Building Construction Project Delays in Osun State, Nigeria

3. Ahmed, S. M., Azhar, S., Castillo, M., & Kappagantula, P. (2002). Construction delays in Florida: An empirical study. Department of Community Affairs, Florida, US.

4. Stakeholders' Perception of the Causes and Effects of Construction Delays on Project Delivery

5. Al-Sultan, A.S. (1989). Determination of construction contract duration for public projects in Saudi Arabia [Doctoral dissertation]. King Fahd University of Petroleum and Minerals.

Cited by 6 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3