DEVELOPING COMPUTER-BASED SCHEDULE DELAY ANALYSIS METHODS BASED ON INFORMATION FLOW ANALYSIS: A CASE STUDY

Author:

Tsai Ming-Kuan1,Yang Jyh-Bin2,Yau Nie-Jia1

Affiliation:

1. Research Center for Hazard Mitigation and Prevention, National Central University, Zhongli, Taiwan

2. Graduate Institute of Construction Engineering and Management, National Central University, Zhongli, Taiwan

Abstract

Schedule analysts often resolve diverse schedule delay problems in construction projects based on their subjective experiences. Although various process-based and mathematical-model schedule delay analysis methods are available for effective schedule delay analysis, these methods require time-consuming manual operation. The use of computer-based schedule delay analysis methods seems to be a solution. However, schedule analysts still have difficulty developing computer-based schedule delay analysis methods. Therefore, this study applies information flow analysis to classify the necessary work to develop computer-based schedule delay analysis methods. In contrast to numerous studies that focus only on computerizing a process-based or a mathematical-model schedule delay analysis method, this study constructs a computer-based method that integrates two process-based schedule delay analysis methods simultaneously. In a tested case study, the delay liability for the project owner and contractor was classified successfully. Importantly, this study provides a useful reference for similar applications in project management.

Publisher

Vilnius Gediminas Technical University

Subject

Strategy and Management,Civil and Structural Engineering

Cited by 9 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. Automated Management of Time Extension Claims;Journal of Legal Affairs and Dispute Resolution in Engineering and Construction;2024-05

2. A comprehensive review of delay analysis techniques for solving concurrent delays;Engineering, Construction and Architectural Management;2024-02-20

3. Exploring the adoption of technology against delays in construction projects;Engineering, Construction and Architectural Management;2022-11-17

4. Joint-Venture Contractor Selection Using Competitive and Collaborative Criteria with Uncertainty;Journal of Construction Engineering and Management;2019-02

5. Using BIM to Identify Claims Early in the Construction Industry: Case Study;Journal of Legal Affairs and Dispute Resolution in Engineering and Construction;2018-08

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3