Abstract
Purpose
For construction and management, the existing codes of practice of international organizations such as US Army Corps of Engineers, the Asian Development Bank, the World Bank, the United Nations Office for Project Services, etc., often prove ineffective when applied in post-war countries like Afghanistan. Domestic contractors faced maximum challenges in contractual scope management, which was implemented by such organizations based on their existing codes of practice. The purpose of this paper is to understand these barriers in scope management as faced by the domestic contractors of Afghanistan.
Design/methodology/approach
The research employs a mixed methodology to cater to its objectives. Face-to-face structured interviews of 14 industry experts and extensive literature review were conducted to identify unique barriers pertaining to Afghanistan construction industry. Further, quantitative assessment of these barriers through the statistical tools of “mean score ranking,” “Kendall’s test” and “independent sample t-test” was carried out to understand the severity of the barriers.
Findings
In total, 39 unique barriers were identified under the groups of “scope formulation,” “scope completeness,” “scope pricing,” “scope implementation” and “scope change control.” The consequential impacts of these barriers and their existence at different stages of the project were illustrated. The most severe barriers were identified as the “inadequacy of site investigation reports” and the “unavailability of resources in local markets.”
Originality/value
The understanding of the challenges faced by local stakeholders, as highlighted by this study, can be utilized by these international organizations in their strategy and planning to ensure successful projects while also propagating the adoption of sustainable construction practices.
Subject
General Business, Management and Accounting,Building and Construction,Architecture,Civil and Structural Engineering
Reference50 articles.
1. Economic reconstruction of Iran: costing the war damage;Third World Quarterly,1990
2. ADB (2015b), “Asian Development Bank Member Fact Sheet”, Asian Development Bank, available at: www.adb.org/countries/afghanistan/main (accessed May 18, 2016).
3. Fundamental uncertainties in projects and the scope of project management;International Journal of Project Management,2006
4. Incorporating uncertainty in competitive bidding;International Journal of Project Management,2000
5. Collaborative negotiation behaviors in Thai construction projects;Journal of Legal Affairs and Dispute Resolution,2011
Cited by
9 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献