Abstract
Purpose
The purpose of this paper is to investigate models and methods for managing supply chain risks and delays in construction projects.
Design/methodology/approach
The study mainly employs quantitative analysis in order to identify disruptions in construction supply chains. It also uses paradigms of simulation modeling, which are suitable for risk assessment and management. Both qualitative and quantitative data were collected through a literature review and details of specific construction projects, respectively. A dynamic modeling method was used, and the model was provided with an event-based simulation. Simulation modeling was used to measure the performance of the system.
Findings
The study shows the benefits of applying the dynamic modeling method to a construction project. Using event-based simulation, it was found that construction delays influence both the magnitude and the probability of disruption. This method contributes to the existing theoretical foundations of risk management practices, since it also considers the time factor. This method supplements the Monte Carlo statistical simulation method, which has no time representation. Using empirical analysis, the study proposes increasing the safety stock of construction materials at the distribution center, so as to mitigate risks in the construction supply chain.
Research limitations/implications
The research considers a single case of a hypothetical construction project. The simulation models represent a simple supply chain with only one supplier. The calculations are based on the current economic scenario, which will of course change over time.
Practical implications
The outcomes of the study show that the introduction of a safety stock of construction materials at the distribution center can prevent supply chain disruption. Since the consideration of risks at all stages of construction supply chain is essential to investors, entrepreneurs and regulatory bodies, the adoption of new approaches for their management during strategic planning of the investment projects is essential.
Originality/value
This dynamic modeling method is used in combination with the Monte Carlo simulation, thus, providing an explicit cause-and-effect dependency over time, as well as a distributed value of outcomes.
Subject
Industrial and Manufacturing Engineering,Strategy and Management,Computer Science Applications,Industrial relations,Management Information Systems
Reference47 articles.
1. MCDA and risk analysis in transport infrastructure appraisals: the Rail Baltica case;Procedia – Social and Behavioral Sciences,2011
2. Combining Monte Carlo simulations and options to manage the risk of real estate portfolios;Journal of Property Investment & Finance,2013
3. Identifying Public-Private Partnership (PPP) risks in managing water supply projects in Ghana;Journal of Facilities Management,2013
4. Sensitivity analysis for property appraisal;Journal of Property Valuation and Investment,1993
Cited by
46 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献