Author:
Oyegoke Adekunle Sabitu,Al Kiyumi Naseer
Abstract
Purpose
Project delay is becoming a problem in the Sultanate of Oman as evidenced by many delayed projects across the country. The purpose of this study is to examine causes and effects of delays in megaprojects in the Sultanate of Oman with recommendations to mitigate same.
Design/methodology/approach
A systematic review of literature identifies through main stakeholders the numerous causes, impacts and methods of mitigating delay from previous studies. A questionnaire survey on Oman was carried out to sample opinions from the practitioners; 53 questionnaires were received and analysed using the relative importance index (RII) method.
Findings
The five most frequent causes of delay in the Sultanate of Oman, in rank order, are: selection of the lowest bid, instead of best bid for the client (RII: 0.698); the financial condition of the main contractor (RII: 0.664); delay in decision-making by the client (RII: 0.656); and poor construction planning by the main contractor (RII: 0.649). Also, the findings indicate that extra cost (RII: 0.754) and project time overrun (RII: 0.724) are the most significant effects of the delay in the Oman megaprojects. The use of experienced contractors and consultant (RII 0.675), efficient construction planning by the main contractor and effective site management and supervision (RII: 0.667) are essential mitigation methods of construction delay in Oman megaprojects.
Originality/value
The study recommends three-part novel solutions to mitigate delay in the Oman construction industry.
Subject
Economics and Econometrics,Finance,Accounting,Business and International Management
Reference43 articles.
1. Delay mitigation in the Malaysian construction industry;Journal of Construction Engineering and Management,2006
2. The effects of construction delays on project delivery in Nigerian construction industry;International Journal of Project Management,2002
3. Construction delays and their causative factors in Nigeria;Journal of Construction Engineering and Management,2006
4. The significant factors causing delay of building construction projects in Malaysia;Engineering, Construction and Architectural Management,2007
5. Al Habsi, Y. (2013), “Toward building an attractive construction industry”, Alwatan, 7 July, available at: www.alwatan.com/graphics/2013/07JUL/26.7/dailyhtml/economy.html#1 (accessed 10 June 2016).
Cited by
38 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献