Preparing a framework for two-stage target-cost arrangement formulation

Author:

Lahdenperä Pertti

Abstract

Purpose – Early involvement of the project team with the construction resources seems to be gaining popularity as it aims to improve the cost efficiency of a project as there is significantly more potential to influence the project solution at that point in time. The missing price during early involvement/selection and the principal-agent setting, however, tend to leave the project owner in doubt of the reasonableness of pricing when it is fixed only later after the joint design phase involving the service provider and the owner. The purpose of this paper is to find a solution for this challenge. Design/methodology/approach – A two-stage target-cost (2STC) arrangement has been proposed as the solution. In this model the service provider earns a bonus by suggesting a lower target cost than the reference set at the time of the involvement of the provider. The amount of bonus also impacts the cost over-run risk transferred to the service provider to avoid overly optimistic promises. The proposition encompassed just the basic idea, and did not really delve into actual model formulations and their functioning under practical realities. Therefore, the required work is presented here in the form of a conceptual, discursive study focusing on relevant theories and empirical findings from major investment projects. Findings – The study produces a requirement framework for the 2STC model to allow functioning models to be formulated and tested. The framework incorporates numerous requirements, constraints and a suggested path forward. For instance, while the model may not be manipulatable, it must incentivise the service provider to seek more cost-effective project solutions, be feasible also from the view of the project owner and adapt to various project risk profiles and ranges of efficiency improvements. Research limitations/implications – The study suggests more concrete model formulations to be provided under the guidance of the presented framework. Originality/value – The 2STC model is a unique concept and no comparable construct is known to exist. Besides the requirement framework, the study also strengthens the foundation of and need for the 2STC model by a thorough survey of its theoretical linkages. Accordingly, the study presented in this paper forms the second stage in the overall 2STC development process focused on benefiting project owners and the industry.

Publisher

Emerald

Subject

Strategy and Management,Business and International Management

Reference101 articles.

1. Aibinu, A. and Pasco, T. (2008), “The accuracy of pre-tender building cost estimates in Australia”, Construction Management and Economics , Vol. 26 No. 12, pp. 1257-1269.

2. Alliance Executive Team (2013), “Rantatunneli alliance project. Project Plan”, Tampere City, Finnish Transport Agency, Lemminkäinen Infra, Saanio & Riekkola and A-Insinöörit Suunnittelu, Tampere.

3. Alliance Executive Team (2014), “Rantatunneli alliance project. Value for money report, project development phase”, Tampere City, Finnish Transport Agency, Lemminkäinen Infra, Saanio & Riekkola, A-Insinöörit Suunnittelu, Tampere.

4. Ashworth, A. and Skitmore, M. (1983), “Accuracy in estimating”, The Chartered Institute of Building, Occasional Paper No. 27, Berkshire.

5. Ball, M. and Chambers, M. (2009), “An incentivisation scheme for a major transportation infrastructure project in the UK”, in Dainty, A. (Ed.), Procs 25th Annual ARCOM Conference, 7-9 September 2009, Nottingham, UK , Association of Researchers in Construction Management, pp. 605-614.

Cited by 13 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. A systematic search and review of early contractor involvement in construction project development;Built Environment Project and Asset Management;2024-08-20

2. Efficiency of project management in higher education establishments on the example of Gdynia Maritime University;Management;2022-08-08

3. Improved reliability in planning large-scale infrastructure project delivery through Alliancing;International Journal of Managing Projects in Business;2022-06-06

4. Critical Factors to Overcome Project Scope Creep in the Oil and Gas Industry;International Journal of Service Science, Management, Engineering, and Technology;2022-04-20

5. Agency relationships of project-based firms;International Journal of Project Management;2021-10

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3