Author:
Nafe Assafi Mohammad,Hossain Md. Mehrab,Chileshe Nicholas,Datta Shuvo Dip
Abstract
Purpose
As a developing nation, Bangladesh still has scarce technological applications in the construction sector, which results in construction delays. This paper aims to propose a framework that will diminish manual labor, reduce human error and apply four-dimensional (4D) building information modeling (BIM)-based solutions to mitigate and prevent construction project delays.
Design/methodology/approach
First, a systematic literature review was conducted on analyzing the construction delay scenario in the context of Bangladesh and other countries. Next, a 4D BIM-based framework was developed using Autodesk Navisworks Manage. Finally, it was used to run on-site simulations on an ongoing construction project which faced delays because of design errors and inefficient planning.
Findings
Affirmative results were found from applying these methods through real-time project simulation. The current status of the project and the status after using BIM technology were compared. It was observed that during both the preconstruction and execution phases, the application of 4D BIM could reduce the delay posed by design error and inefficient planning.
Practical implications
The project manager and the design engineers can use these frameworks to review their projects. For the design engineers, the preconstruction phase portion of the framework will help identify the probable errors in the design. For the project managers, keeping track of time using the execution phase portion of the framework will be resourceful.
Originality/value
To the best of the authors’ knowledge, this study is the first to assess the significant delay factors endemic in Bangladesh and develop a BIM-based technological solution. This study is solely dedicated to reforming the construction techniques in Bangladesh through the application of 4D BIM technology.
Subject
Building and Construction,Architecture,Civil and Structural Engineering,General Computer Science,Control and Systems Engineering
Reference75 articles.
1. Building information modelling (BIM) adoption and implementation enablers in AEC firms: a systematic literature review;Architectural Engineering and Design Management,2021
2. Analysis of cost and schedule performance of international development projects;International Journal of Project Management,2010
3. Factors affecting as barrier for adaptation of building information modelling in architecture practice in Bangladesh;SEU Journal of Science and Engineering,2020
4. Ranking of the factors causing cost overrun in infrastructural projects of UAE;International Journal of Sustainable Construction Engineering and Technology,2020
5. A project control process in pre‐construction phases: focus on effective methodology;Engineering, Construction and Architectural Management,2005
Cited by
13 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献