Purpose
The consideration of external stakeholders has proven to be more critical than internal stakeholders in construction projects. The purpose of this paper is to present the diverse expectations of external stakeholder groups, i.e. governmental authorities, general public, and affected local communities, in construction projects. The practical steps to manage the expectations are also outlined.
Design/methodology/approach
A three-stage methodology was adopted for the review. The primary terms “stakeholder,” “project participants,” or “project environment” were first searched in four popularly search engines and eight top journals that publish construction research to retrieve publications. After a second-stage filtering process, the selected data were then analyzed and reviewed in line with the objectives.
Findings
In total, 49 common expectations were identified and classified. The results indicate that each stakeholder group pursues expectations in line with the social, environmental, and economic sustainability objectives. For effective management, project managers (PMs) must know stakeholder opportunities and threats, fulfill social responsibilities, establish common goals, apply appropriate strategies, and enhance stakeholder satisfaction.
Research limitations/implications
The identified expectations are only based on the selected publications. Even though the expectations have been categorized in line with the triple bottom line model, the relative importance of the expectations cannot be ascertained since there is no empirical support.
Practical implications
PMs can play safe by acknowledging the stakeholder expectations and employ such strategies to curtail resulting impacts and maximize mutual benefits. The list of expectations could also be used to promote equitable value optimization in projects, enhance needs fulfillment, and facilitate the evaluation of external stakeholder satisfaction.
Originality/value
This study provides a comprehensive checklist of construction stakeholder expectations which hitherto, is lacked in the literature. Moreover, practical steps to manage the expectations of external stakeholders have been discussed.
Subject
General Business, Management and Accounting,Building and Construction,Architecture,Civil and Structural Engineering
Reference87 articles.
1. Project stakeholder analysis as an environmental interpretation process;International Journal of Project Management,2011
2. Response strategies to stakeholder pressures in global projects;International Journal of Project Management,2009
3. Stakeholder salience in global projects;International Journal of Project Management,2008
4. Assessment of social sustainability in construction projects using social network analysis;Facilities,2015
5. Public participation in sustainable urban planning;International Journal of Civil, Environmental, Structural, Construction and Architectural Engineering,2009
Cited by
46 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献