Neural network models for actual duration of Greek highway projects

Author:

Titirla Magdalini,Aretoulis Georgios

Abstract

Purpose This paper aims to examine selected similar Greek highway projects to create artificial neural network-based models to predict their actual construction duration based on data available at the bidding stage. Design/methodology/approach Relevant literature review is presented that highlights similar research approaches. Thirty-seven highway projects, constructed in Greece, with similar type of available data, were examined. Considering each project’s characteristics and the actual construction duration, correlation analysis is implemented, with the aid of SPSS. Correlation analysis identified the most significant project variables toward predicting actual duration. Furthermore, the WEKA application, through its attribute selection function, highlighted the most important subset of variables. The selected variables through correlation analysis and/or WEKA and appropriate combinations of these are used as input neurons for a neural network. Fast Artificial Neural Network (FANN) Tool is used to construct neural network models in an effort to predict projects’ actual duration. Findings Variables that significantly correlate with actual time at completion include initial cost, initial duration, length, lanes, technical projects, bridges, tunnels, geotechnical projects, embankment, landfill, land requirement (expropriation) and tender offer. Neural networks’ models succeeded in predicting actual completion time with significant accuracy. The optimum neural network model produced a mean squared error with a value of 6.96E-06 and was based on initial cost, initial duration, length, lanes, technical projects, tender offer, embankment, existence of bridges, geotechnical projects and landfills. Research limitations/implications The sample size is limited to 37 projects. These are extensive highway projects with similar work packages, constructed in Greece. Practical implications The proposed models could early in the planning stage predict the actual project duration. Originality/value The originality of the current study focuses both on the methodology applied (combination of Correlation Analysis, WEKA, FannTool) and on the resulting models and their potential application for future projects.

Publisher

Emerald

Subject

General Engineering

Reference37 articles.

1. A taxonomy of planning and scheduling methods to support their more efficient use in construction project management;Journal of Engineering, Design and Technology,2016

2. Right-of-way acquisition duration prediction model for highway construction projects;Journal of Construction Engineering and Management,2011

3. Empirical assessment of the likelihood and duration of highway project time delays;Journal of Construction Engineering and Management,2011

4. Examination of project duration, project intensity, and timing of cost certainty in highway project delivery methods;Journal of Management in Engineering,2018

5. Application of the multi attribute utility theory for the selection of project procurement system for Greek highway projects;International Journal of Management and Decision Making,2016

Cited by 8 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3