Owner and contractor solution strategies for industrial commissioning

Author:

Mock Brant,O’Connor James T.

Abstract

Purpose The purpose of this study is to discover which solution strategies to common industrial commissioning and startup (CSU) problems (Hot Spots) owner and contractor organizations identify as most effective and to identify which strategies are identified by one or both organization types. Design/methodology/approach Ratings for the relative value provided by strategies, and the effort required to implement strategies were solicited from CSU industry experts employed by owner or contractor organizations via a survey. Quantitative modelling using the Possible, Implement, Challenge, Kill (PICK) chart method distinguished high-value, low-effort strategies from other strategies. Findings Owners and contractors identify distinct sets of CSU solution strategies as high value and low effort, with some overlap. Of 178 total strategies, 40 (22.5 per cent) were identified by owners and 34 (19.1 per cent) by contractors, with 19 (10.7 per cent) of those strategies in common. Strategies with the greatest differences in opinions between owners and contractors are also identified. Research limitations/implications Research findings are limited to industrial-type, operational systems-intensive facilities. Similarities may exist with other systems-intensive project types, such as some commercial or infrastructure projects. The survey sample size is relatively small (n = 35), but close to that of other CSU-related surveys. The majority of survey participants were based in North America at the time of participation. Further, the number of contractor and owner participants differed slightly. Practical implications CSU managers and personnel should consider using high-value, low-effort strategies before resorting to other less effective strategies, as applicable on their projects. Depending on which organization is executing CSU, or if both organization types share CSU responsibilities, different solution strategies may be most effective. Originality/value Differences in owner and contractor perspectives and opinions have been noted in other aspects of the project lifecycle but never for CSU solution strategies. Use of the strategies identified will support more effective CSU execution.

Publisher

Emerald

Subject

Building and Construction,Architecture,Civil and Structural Engineering,General Computer Science,Control and Systems Engineering

Reference60 articles.

1. Holm’s sequential bonferroni procedure,2012

2. Analysis of factors influencing project cost estimating practice;Construction Management and Economics,2000

3. BIM for client organisations: a continuous improvement approach;Construction Innovation,2015

4. Statistical tests,2017

5. Deal with start-up and commissioning threats and challenges at an early stage of the project for a sucessful handover and project completion,2012

Cited by 8 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3