Resource overload problems with tardiness penalty: structural properties and solution approaches

Author:

Wohlert Lena SophieORCID,Zimmermann Jürgen

Abstract

AbstractIn this paper, we consider a resource overload problem and add a tardiness penalty to the objective function when a prescribed project makespan is exceeded, which enables a trade-off between a balanced resource utilization and a project delay. For the tardiness penalty, we distinguish between a constant and variable delay cost variant. Based on the structural properties of the resource overload problem, we show that the search space of the resource overload problem with tardiness penalty can also be reduced utilizing quasistable schedules. In addition, we discuss the application of these findings to further problems, which include objectives composed of a locally concave and a concave function or a reward structure for an early project completion instead of a tardiness penalty. As solution approaches, we present mixed-integer linear model formulations as well as a novel genetic algorithm with a decoding procedure, which exploits the devised structural properties. The performance of the genetic algorithm is improved by implementing learning methods and utilizing lower bounds. Finally, we present results from experiments on small to medium sized problem instances.

Funder

Technische Universität Clausthal

Publisher

Springer Science and Business Media LLC

Reference24 articles.

1. Abbasi Iranagh, M. (2015). Development of high performance heuristic and meta-heuristic methods for resource optimization of large scale construction projects. Ph.D. thesis, Middle East Technical University.

2. Ahuja, R. K., Magnanti, T. L., & Orlin, J. B. (1993). Network flows. Prentice Hall.

3. Atan, T., & Eren, E. (2018). Optimal project duration for resource leveling. European Journal of Operational Research, 266(2), 508–520.

4. Ballestin, F., Schwindt, C., & Zimmermann, J. (2007). Resource leveling in make-to-order production: Modeling and heuristic solution method. International Journal of Operations Research, 4(1), 50–62.

5. Bianco, L., Caramia, M., & Giordani, S. (2016). Resource levelling in project scheduling with generalized precedence relationships and variable execution intensities. OR Spectrum, 38, 405–425.

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3