Abstract
AbstractThis paper addresses the questions: How to calculate the cost of a start/stop cycle? How to calculate the cost of running one hour outside normal operating range, e.g., on part load? The paper presents a model for calculation of start/stop cost for individual hydropower units comprising both direct costs incurring at each start/stop cycle, and indirect cost because of reduced rehabilitation intervals for the main components. The fundamental assumption is that frequent start-ups lead to increased stress, degradation and wear reducing residual service life equivalent to a certain number of normal operating hours, thus accelerating the need for rehabilitation. The proposed model is used for calculation of both average cost and marginal cost for one start/stop cycle. When calculating the marginal cost, the technical condition of the turbine and generator as well as the length of the stand-still period can be considered. Applying a similar approach, the model is extended to calculate the cost of ramping, part load and overload operation, i.e., costs incurring when using the unit outside the normal operating range. This extension for operation related costs is important to include when deciding hydropower scheduling in systems with large shares of variable generation from wind and solar. Such operation related costs are very important to consider when calculating of the optimal operating strategy for the hydropower units in power systems where hydropower delivers flexibility in terms of load following and different types of reserves.
Publisher
Springer Science and Business Media LLC
Subject
General Energy,Economics and Econometrics,Modeling and Simulation
Reference14 articles.
1. Nilsson, O., Sjelvgren, D.: Hydro unit start-up costs and their impact on the short term scheduling strategies of Swedish power producers. IEEE Trans. Power Syst. 12(1), 38–44 (1997). https://doi.org/10.1109/59.574921
2. Bureau of Reclamation, Hydrogenerator Start/Stop Costs, U.S. Department of the Interior, Bureau of Reclamation, Technical Service Center (2014)
3. Savin, O., Badina, C., Baroth, J., Charbonnier, S., Bérenguer, C.: Start and stop costs for hydro power plants: a critical literature review. In: Proceedings of the 30th European Safety and Reliability Conference and the 15th Probabilistic Safety Assessment and Management Conference (2020)
4. Savin, O.: Effet des cycles de démarrages et d’arrêts sur les centrales hydrauliques: modélisation de la détérioration des matériels pour l’évaluation des coûts de cyclage, PhD Thesis, Université Grenoble Alpes. https://theses.hal.science/tel-03606368 (2021)
5. Savin, O., Badina, C., Pollier, R., Drommi, J.-L., Baroth, J., Charbonnier, S., Berenguer, C.: Effect of start and stop cycles on hydropower plants: modelling the deterioration of the equipment to evaluate the cycling cost. IOP Conf. Ser. Earth Environ. Sci. 1136(1), 012057 (2023). https://doi.org/10.1088/1755-1315/1136/1/012057