Ground improvement techniques for railway embankments

Author:

Arulrajah A.1,Abdullah A.2,Bo M. W.3,Bouazza A.4

Affiliation:

1. Civil Engineering, Faculty of Engineering and Industrial Sciences, Swinburne University of Technology Melbourne, Australia

2. Ranhill Consulting Kuala Lumpur Malaysia

3. DST Consulting Engineers Inc. Ontario, Canada

4. Department of Civil Engineering, Monash University Melbourne, Australia

Abstract

A high-speed railway project for trains of speeds of up to 160 km/h is currently being constructed between Rawang and Bidor (110 km long) in Peninsular Malaysia. The ground improvement methods adopted in the project are vibro-replacement with stone columns, dry deep soil mixing (cement columns), geogrid-reinforced piled embankments with individual pile caps and removal/replacement works. This paper provides a detailed insight into the design and implementation of vibro-replacement and the deep soil mixing treatment methods used in the project. The use of plate bearing tests and field instrumentation to monitor the performance of the stone columns and soil mixing ground treatment methods is also discussed. This paper also provides a brief overview of other treatment methods implemented in this high-speed railway project such as a pile embankment with geogrids and removal/replacement works.

Publisher

Thomas Telford Ltd.

Subject

Mechanics of Materials,Soil Science,Geotechnical Engineering and Engineering Geology,Building and Construction

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3