Construction time and cost for post-tensioned timber buildings

Author:

Smith T.1,Fragiacomo M.2,Pampanin S.3,Buchanan A. H.4

Affiliation:

1. Research student, University of CanterburyNew Zealand

2. Associate Professor, University of SassariItaly

3. Associate Professor, University of CanterburyNew Zealand

4. Professor, University of CanterburyNew Zealand

Abstract

This paper describes post-tensioned timber alternative designs for a six-storey office building in New Zealand. The building has long-span timber–concrete composite floors supported on laminated veneer lumber beams, columns and walls. Lateral loads are resisted with moment-resisting post-tensioned timber frames in one direction and post-tensioned cantilever timber walls in the other direction. This paper compares the time and cost of timber construction with the concrete building actually being constructed. Construction times of the timber and concrete buildings are found to be almost identical. The cost of the timber alternative is approximately 6% more than concrete or steel designs. This paper demonstrates the opportunity for post-tensioned timber to compete with concrete and steel for multi-storey long-span office buildings, providing a more sustainable alternative.

Publisher

Thomas Telford Ltd.

Subject

Mechanics of Materials,General Materials Science,Civil and Structural Engineering

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3