Affiliation:
1. Skanska UK Building London, UK
2. Geotechnical Engineering Research Centre, City University London, UK
3. WJ Groundwater Limited Bushey, UK
4. Arup Geotechnics London, UK
Abstract
An 8·2 m diameter, 37·5 m deep shaft has been successfully constructed from within the basement of a new development, Moorhouse, near Moorgate in the City of London. Programme constraints led to the shaft being constructed after completion of the foundations, basements and most of the superstructure for the development. At its closest point the shaft is less than 2 m from the large-diameter piles that support Moorhouse, and the presence of these foundations placed tight constraints on acceptable ground movements associated with construction of the shaft. The depth of the shaft is such that it penetrates through stiff London Clay and is founded at the bottom of the Lambeth Group. The paper describes the contingency measures to deal with potentially difficult ground conditions, including the water-bearing layers of the Lambeth Group. The construction processes included a complex temporary works dewatering system around the shaft, with the option to carry out additional dewatering from within the shaft during excavation. Provision was also made for radial grouting to ‘restress’ the ground, to prevent long-term settlement of the Moorhouse piles, should the need arise. The success of the project was due, in no small part, to the detailed planning and consideration of contingency measures to deal with perceived risk.
Subject
Earth and Planetary Sciences (miscellaneous),Geotechnical Engineering and Engineering Geology
Cited by
8 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献