Developing a Preliminary Engineering Cost Estimation Method for a Portfolio of Bridge Construction Projects in Project Planning Phase

Author:

Son Junghye1ORCID,Khwaja Nabeel1ORCID

Affiliation:

1. Center for Transportation Research, The University of Texas at Austin, Austin, TX

Abstract

For state departments of transportation (DOTs), estimating preliminary engineering (PE) costs over a multiple-year horizon is critical for proper planning of engineering resources and budgets to ensure timely delivery of a portfolio of bridge construction projects, which incur PE costs that are relatively higher than those required for other highway project types. However, given the uncertainties in the planning phase, it is challenging to estimate PE costs effectively and efficiently. The purpose of this study was to provide DOTs with a PE cost estimation method using different ratios of PE cost to construction cost for bridge projects by project type and size. To that end, the study tested the variability of PE costs by analyzing 628 Texas DOT bridge construction projects divided into three project types: bridge maintenance (BMN), bridge replacement (BR), and bridge widening and rehabilitation (BWR). The analysis found that the ratios of PE cost to construction cost for the BMN and BR project types were significantly different by project size, but was not conclusive for the BWR project type because of limited sample size. The validation results indicate that the proposed method is effective for planning and estimating the PE costs of a portfolio of projects. The study findings can provide DOTs with an improved PE cost estimation process for a portfolio of bridge projects during the project planning phase.

Publisher

SAGE Publications

Subject

Mechanical Engineering,Civil and Structural Engineering

Reference21 articles.

1. FHWA Memorandum. Guidance on Preliminary Engineering Authorizations in FMIS. Federal Highway Administration, U.S. Department of Transportation, 2015. https://www.fhwa.dot.gov/federalaid/150311.cfm. Accessed April 1, 2021.

2. Federal Highway Administration. FHWA Does Not Effectively Ensure States Account for Preliminary Engineering Costs and Reimburse Funds as Required. FHWA Report: ST-2016-095. FHWA, U.S. Department of Transportation, 2016. https://www.oig.dot.gov/sites/default/files/FHWA%20Oversight%20of%20Preliminary%20Engineering%20Final%20Report%5E8-25-16.pdf. Accessed April 1, 2021.

3. Gransberg D., Jeong H. D., Craigie E. K., Rueda-Benavides J. A., Shrestha K. J. Estimating Highway Preconstruction Services Costs. Volume 1: Guidebook. The National Academies Press, Washington, D.C., 2016. https://doi.org/10.17226/23590.

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3