Lock-in and its Influence on the Project Performance of Large-Scale Transportation Infrastructure Projects: Investigating the Way in Which Lock-in Can Emerge and Affect Cost Overruns

Author:

Cantarelli Chantal C1,Flyvbjerg Bent2,van Wee Bert1,Molin Eric J E1

Affiliation:

1. Faculty of Technology, Policy, and Management, Delft University of Technology, Jaffalaan 5, 2628 BX Delft, The Netherlands

2. BT Centre for Major Programme Management, Saïd Business School, University of Oxford, Park End Street, Oxford OX1 1HP, England

Abstract

Lock-in, the escalating commitment of decision makers to an ineffective course of action, has the potential to explain the large cost overruns in large-scale transportation infrastructure projects. Lock-in can occur both at the decision-making level (before the decision to build) and at the project level (after the decision to build) and can influence the extent of overruns in two ways. The first involves the ‘methodology’ of calculating cost overruns according to the ‘formal decision to build’. Due to lock-in, however, the ‘real decision to build’ is made much earlier in the decision-making process and the costs estimated at that stage are often much lower than those that are estimated at a later stage in the decision-making process, thus increasing cost overruns. The second way that lock-in can affect cost overruns is through ‘practice’. Although decisions about the project (design and implementation) need to be made, lock-in can lead to inefficient decisions that involve higher costs. Sunk costs (in terms of both time and money), the need for justification, escalating commitment, and inflexibility and the closure of alternatives are indicators of lock-in. Two case studies, of the Betuweroute and the High Speed Link-South projects in the Netherlands, demonstrate the presence of lock-in and its influence on the extent of cost overruns at both the decision-making and project levels. This suggests that recognition of lock-in as an explanation for cost overruns contributes significantly to the understanding of the inadequate planning process of projects and allows development of more appropriate means.

Publisher

SAGE Publications

Subject

General Environmental Science,Geography, Planning and Development

Cited by 71 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3