The Parallel Machine Scheduling with Considering the Due Date Assignment, Earliness, Weighted Number of Tardy Jobs and Batch Delivery

Author:

Fakhrzad M. B.1,Shamsadini Saber2,Jafari-Nodoushan Abbasali3

Affiliation:

1. Department of Industrial Engineering, Faculty of Engineering, Yazd University, Yazd, Iran

2. M.S. Student of Industrial Engineering, Faculty of Engineering, Yazd University, Iran

3. Department of Industrial Engineering, Faculty of Engineering, Meybod University, Meybod, Iran

Abstract

In this paper, parallel machine scheduling problem is considered under due date assignment, earliness, weighted number of tardy jobs, facilities costs and shipping products by limited vehicle capacity. The orders of the customer are presented with a due date. Each order is scheduled and assigned to one of the machines according to due date, delay weight and penalty of increasing of due date and shipped in the batch. The problem is known as NP-hardness, therefore a Genetic Algorithm (GA) is proposed to solve the problem. The results are also compared with the CPLEX solver in the GAMS. Finally, sensitivity analysis for the problem parameters is performed in relation to the objective function. The results showed a direct relationship between objective function with the weighted tardiness and processing time, also an inverse relationship with the number of machines and vehicle capacity.

Publisher

World Scientific Pub Co Pte Lt

Subject

Industrial and Manufacturing Engineering,Strategy and Management,Computer Science Applications

Cited by 1 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3