This article presents the problems of guaranteeing high work productivity in the digging or cleaning of ditches and collectors, as well as the implementation of design indicators, as specified in the project, and measures to eliminate them using modern innovative technologies. Ditch and collectors work at the level of demand, improve land reclamation conditions, increase productivity and reduce the volume of additional earthworks, increase economic efficiency to high levels. The results of the conducted scientific research showed that during the construction of the open pit, the volume of earthworks was reduced by 15%, and the carrying capacity of the stream was increased by 25%. As a result, it makes it possible to increase the reliability and maintain the technical condition of using open pits.