Optimization on Resource-Constrained Multi-Project Scheduling of Electric Multiple Unit Overhaul

Author:

Sun Peng1,Shi Tian Yun1,Zhang Wei Jiao1

Affiliation:

1. China Academy of Railway Sciences

Abstract

As the numbers and running distance of Chinese high-speed trains increase, many electric multiple units (EMU) gradually enter into overhaul stage, EMU maintenance bases face challenges of transition from practical exploration, regular production to lean production. In accordance of business requirement, built a model of dynamic resource allocation, task splitting, and soft precedence constraints. By the design of nonlinear decline inertia weight factor, a refined particle swarm optimization (PSO), as well as the corresponding parallel transformation scheme from particle to schedule, is presented. Finally, computational analysis is performed to validate the model and algorithm on optimization capabilities, resource utilization and performance.

Publisher

Trans Tech Publications, Ltd.

Subject

General Engineering

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. Model and algorithm for the first-level maintenance operation optimization of EMU trains;Journal of Intelligent & Fuzzy Systems;2021-08-11

2. Applications of particle swarm optimization in the railway domain;International Journal of Rail Transportation;2016-04-27

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3