Do Projects really end late? On the shortcomings of the classical scheduling techniques

Author:

Ballesteros-Pérez PabloORCID,Larsen Graeme D.ORCID,González-Cruz Maria C.ORCID

Abstract

Many engineering projects fail to meet their planned completion dates in real practice. This a recurrent topic in the project management literature, with poor planning and controlling practices frequently cited among the most significant causes of delays. Unfortunately, hardly any attention has been paid to the fact that the classical scheduling techniques: Gantt chart, Critical Path Method (CPM), and Program Evaluation and Review Technique (PERT), may not be as fit for purpose as they seem. Arguably, because of their relative simplicity, these techniques are still almost the only ones taught nowadays in most introductory courses to scheduling in many engineering and management degrees. However, by utterly ignoring or inappropriately dealing with activity duration variability, these techniques provide optimistic completion dates, while suffering from other shortcomings. Through a series of simple case studies that can be developed with a few participants and common dice, a systematic critique of the classical scheduling techniques is offered. Discussion of the case studies results illustrate why limiting the contents of scheduling education and teaching can be detrimental, as the aforementioned classical scheduling techniques cannot not provide project managers with sufficient resources to effectively plan and control real projects.

Publisher

Omnia Publisher SL

Subject

Education

Cited by 15 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. Dynamics of Technical and Technological Processes in Construction under Conditions Of Stochastic Impacts;Russian Journal of Building Construction and Architecture;2024-05-15

2. Project Scheduling a Critical Review of Both Traditional and Metaheuristic Techniques;Studies in Computational Intelligence;2024

3. A Model to Predict Span Time and Effort for Product Development Processes;IFIP Advances in Information and Communication Technology;2024

4. The Approach of Project Critical Path Calculation in the Schedule Management;2023 IEEE 12th International Conference on Intelligent Data Acquisition and Advanced Computing Systems: Technology and Applications (IDAACS);2023-09-07

5. Critical Duration Index: Anticipating Project Delays from Deterministic Schedule Information;Journal of Construction Engineering and Management;2022-11

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3