A semi-automated approach to generate 4D/5D BIM models for evaluating different offshore oil and gas platform decommissioning options

Author:

Cheng Jack C. P.,Tan YiORCID,Song Yongze,Liu Xin,Wang Xiangyu

Abstract

Abstract Background Offshore oil and gas platforms generally have a lifetime of 30 to 40 years, and platform decommissioning is a major issue because many of the existing offshore oil and gas platforms are reaching the end of their service life. There are many possible options for decommissioning offshore oil and gas platforms, and each decommissioning option can be implemented using different methods and technologies. Therefore, it is necessary to have a clear understanding and in-depth evaluation of each decommissioning option before commencing platform decommissioning. 4D and 5D building information modeling (BIM) has been commonly used in the building industry to analyze constructability and to evaluate different construction or demolition plans. However, application of BIM in the oil and gas industry, especially for the platform decommissioning process, is still limited. Methods This paper suggests and demonstrates the application of 4D and 5D BIM technology to simulate various methodologies to realize various selected offshore platform decommissioning options, thereby visualizing and evaluating different options, considering both the time and resources required for decommissioning process. One hundred and seventy-seven offshore platform decommissioning options are summarized in this paper. A new approach to create multiple 4D/5D BIM models in a semi-automated manner for evaluating various scenario options of OOGP decommissioning was proposed to reduce the model creation time as current way of 4D/5D BIM model creation for each OOGP decommissioning option is time consuming. Results In the proposed approach, an OOGP BIM model relationship database that contains possible 4D/5D BIM model relationships (i.e. schedules for different decommissioning methods) for different parts of an OOGP was generated. Different OOGP decommissioning options can be simulated and visualized with 4D/5D BIM models created by automatically matching schedules, resources, cost information and 3D BIM models. This paper also presents an illustrative example of the proposed approach, which simulates and evaluates two decommissioning options of a fixed jacket platform, namely Rig-to-Reef and Removal-to-Shore. As compared to the traditional approach of 4D/5D BIM model generation, the proposed semi-automated approach reduces the model generation time by 58.8% in the illustrative example. Conclusions The proposed approach of semi-automated 4D/5D BIM model creation can help understand the implication of different decommissioning options as well as applied methods, detecting potential lifting clashes, and reducing 4D/5D BIM model creation time, leading to better planning and execution for the decommissioning of offshore oil and gas platforms. In addition, with the proposed semi-automated approach, the 4D/5D BIM model can be generated in a more efficient manner.

Funder

Australian Research Council Linkage Project

Publisher

Springer Science and Business Media LLC

Subject

Computer Graphics and Computer-Aided Design,Computer Science Applications,Computer Vision and Pattern Recognition,Engineering (miscellaneous),Modelling and Simulation

Cited by 18 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3