Barriers and facilitators for BIM use among Swedish medium-sized contractors - “We wait until someone tells us to use it”

Author:

Bosch-Sijtsema Petra,Isaksson Anders,Lennartsson Martin,Linderoth Henrik C. J.ORCID

Abstract

Abstract Background The pace of diffusion of BIM (Building Information Modelling) use is considered to increase with governmental initiatives in which public clients in countries like Finland, Singapore, United Kingdom, and Sweden begin requiring BIM as a part of the project delivery. Currently, larger contractor firms use BIM to a certain extent. However, BIM use by mid-sized contractor firms (that is, firms with 50–500 employees that can successfully compete with larger contractors on projects costing a maximum of 50 million Euros) is relatively unknown. Hence, the aim of the paper is to explore current use and perceived constraints and driving forces of BIM-implementation with respect to mid-sized contractors. Methods A mixed method approach was applied, and data was collected through an interview study and a survey involving chief executive officers or their closest sub-ordinates in mid-sized contractor firms in Sweden. The survey was based on a technology-, organization-, and environment framework that is used in information systems research to study the use of inter-organizational information systems. The total population of firms in the survey corresponded to 104. The study presented the preliminary results based on 32 answers (with a 31% response rate). Results Fifty-eight percent of the surveyed respondents stated that they had been involved in a project in which BIM was used in some manner. The most commonly used application included visualization, which also facilitates coordination and communication. The biggest perceived constraints involved partners that did not use BIM, lack of demand from clients, and the absence of internal demand in the company. With respect to the two last obstacles, significant differences existed between users and non-users. The most common perceived driving forces included the fact that BIM is perceived as a means to follow technical development and that BIM provides competitive advantages to the company. Conclusions It is concluded that the main driver responsible for BIM-implementation is mainly determined by an individual’s subjective positive or negative evaluation of BIM, instead of external pressure from clients and partners or by the internal capacity and knowledge to use BIM.

Publisher

Springer Science and Business Media LLC

Subject

Computer Graphics and Computer-Aided Design,Computer Science Applications,Computer Vision and Pattern Recognition,Engineering (miscellaneous),Modelling and Simulation

Cited by 62 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3