Power-to-gas is the pivotal link between electricity and gas infrastructure, enabling the broader integration of renewable energy. Yet, enhancements are necessary for its full potential. In the biomethanation process, transferring H2 into the liquid phase is a rate-limiting step. To address this, we developed a novel tubular foam-bed reactor (TFBR) and investigated its performance at laboratory scale.
Results
A non-ionic polymeric surfactant (Pluronic® F-68) at 1.5% w/v was added to the TFBR’s culture medium to generate a stabilized liquid foam structure. This increased both the gas–liquid surface area and the bubble retention time. Within the tubing, cells predominantly traveled evenly suspended in the liquid phase or were entrapped in the thin liquid film of bubbles flowing inside the tube. Phase (I) of the experiment focused primarily on mesophilic (40 °C) operation of the tubular reactor, followed by phase (II), when Pluronic® F-68 was added. In phase (II), the TFBR exhibited 6.5-fold increase in biomethane production rate (MPR) to 15.1 $$({\text{L}}_{{\text{CH}}_{4}}\text{/}{\text{L}}_{\text{R}}\text{/d)}$$
(
L
CH
4
/L
R
/d)
, with a CH4 concentration exceeding 90% (grid quality), suggesting improved H2 transfer. Transitioning to phase (III) with continuous operation at 55 °C, the MPR reached 29.7 $${\text{L}}_{{\text{CH}}_{4}}\text{/}{\text{L}}_{\text{R}}\text{/d}$$
L
CH
4
/L
R
/d
while maintaining the grid quality CH4. Despite, reduced gas–liquid solubility and gas–liquid mass transfer at higher temperatures, the twofold increase in MPR compared to phase (II) might be attributed to other factors, i.e., higher metabolic activity of the methanogenic archaea.
To assess process robustness for phase (II) conditions, a partial H2 feeding regime (12 h 100% and 12 h 10% of the nominal feeding rate) was implemented. Results demonstrated a resilient MPR of approximately 14.8 $${\text{L}}_{{\text{CH}}_{4}}\text{/}{\text{L}}_{\text{R}}\text{/d}$$
L
CH
4
/L
R
/d
even with intermittent, low H2 concentration.
Conclusions
Overall, the TFBR’s performance plant sets the course for an accelerated introduction of biomethanation technology for the storage of volatile renewable energy. Robust process performance, even under H2 starvation, underscores its reliability. Further steps towards an optimum operation regime and scale-up should be initiated. Additionally, the use of TFBR systems should be considered for biotechnological processes in which gas–liquid mass transfer is a limiting factor for achieving higher reaction rates.
Funder
European Regional Development Fund
German Federal Ministry of Education and Research
Hochschule Anhalt
Publisher
Springer Science and Business Media LLC
Reference57 articles.
1. European Commission. 2050 Long-Term Strategy (2020). https://ec.europa.eu/clima/eu-action/climate- strategies-targets/2050-long-term- strategy_en Accessed 19 Oct 2021.
2. Blanco H, Faaij A. A review at the role of storage in energy systems with a focus on power to gas and long-term storage. Renew Sustain Energy Rev. 2018;81:1049–86.
3. Thema M, Bauer F, Sterner M. Power-to-gas: electrolysis and methanation status review renew. Sustain Energy Rev. 2019;112(775):87.
4. Rafrafi Y, Laguillaumie L, Dumas C. Biological methanation of H2 and CO2 with mixed cultures: current advances, hurdles and challenges. Waste Biomass Valoriz. 2021;12:5259–82.
5. Ullah Khan I, Hafiz Dzarfan Othman M, Hashim H, Matsuura T, Ismail AF, Rezaei-DashtArzhandi M, et al. Biogas as a renewable energy fuel—a review of biogas upgrading, utilisation and storage. Energy Convers Manag. 2017;150:277–94.