Parameters and surrounding rock control of gob-side driving under double key stratum after roof cutting

Author:

Xu Lei,Ma Yuzhao,Elmo Davide,Ding Shuxue,Zhu Hengzhong,Liu Honglin,Li Wenfeng,Chen Wen

Abstract

AbstractTaking the return-airway 4204 with roof cutting in Longquan Coal Mine as the engineering background, roof structure, key parameters, and deviatoric stress evolution were studied. Conclusion: The Key Stratum within a 4–8 times mining height is considered as Near Key Stratum. Cutting the roof makes it possible to form a cantilever structure of the Key Stratum on the solid coal side, which is more conducive to the stability of gob-side roadway. During cutting angle of 90–55°, the deviatoric stress increases linearly, and the increase rate is coal pillar > solid coal > roof > floor. While cutting length from 0 to 35 m, the deviatoric stress decreases linearly, and the decreasing range: coal pillar > solid coal > roof > floor. When coal pillar width is from 30 to 4 m, the deviatoric stress of left side and floor presents a “single peak” distribution. The deviatoric stress of coal pillar changes from an asymmetric “double peak” to a bell-shaped distribution, and the deviatoric stress of roof changes from a “single peak” to an asymmetric “double peak” distribution. Under same coal pillar width, the deviatoric stress of left, coal pillar and roof after roof cutting decreases most obviously, followed by the floor. Finally, the coal pillar width is 8 m, the cutting angle is 75°, the cutting length is 20 m, and the hole spacing is 1.0 m. The support scheme is bolt + metal mesh + steel belt + anchor cable combined support. The stable period of roadway is about 10 days.

Funder

the National Natural Science Foundation of China

Publisher

Springer Science and Business Media LLC

Reference26 articles.

1. Cheng, L. et al. Deformation and failure characteristics and control technology of surrounding rocks in deeply gob-side entry driving. J. Min. Saf. Eng. 38, 227–236 (2021).

2. Zhang, B., Wang, P., Cui, S., Fan, M. & Qiu, Y. Mechanism and surrounding rock control of roadway driving along gob in shallow-buried, large mining height and small coal pillars by roof cutting. J. China Coal Soc. 46, 2254–2267 (2021).

3. Zhang, H. et al. Stability control of narrow coal pillars in the fully-mechanized gob-side entry during sequenced top coal caving mining. J. China Coal Soc. 46, 1211–1219 (2021).

4. Maes, K., Salens, W., Feremans, G., Segher, K. & François, S. Anomaly detection in long-term tunnel deformation monitoring. Eng. Struct. 250, 1–14 (2022).

5. Rashed, G., Mohamed, K. & Kimutis, R. A coal rib monitoring study in a room-and-pillar retreat mine. Int. J. Min. Sci. Technol. 31, 127–135 (2021).

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3