Schedule risk model of water intake tunnel construction considering mood factors and its application

Author:

Li Xin,Sun Wei,Fu Honggang,Bu Qingsheng,Zhang Zhiguang,Huang Jian,Zang Dongnian,Sun Yuan,Ma Yong,Wang Rui,Hu Jingjing,Shen Yanan

Abstract

AbstractThe mood index $$r$$ r was used to describe evaluator attitudes regarding the progress of a project that formed the basis of a construction period prediction model. The degrees of pessimism $$\alpha$$ α and optimism $$\beta$$ β were introduced, and an analysis model was established using $$\alpha$$ α and $$\beta$$ β to predict the construction period and completion probability Firstly, the absolute construction period of each process of tunnel No. 2 can be obtained according to the measured daily average footage of each process of tunnel No. 1. Secondly, the probability of the stoppage caused by different factors can be obtained after the statistical analysis of the factors responsible for the stoppage of tunnel No. 1. Finally, the expected construction period and completion probability of tunnel No. 2 under different pessimism and optimism conditions are obtained by using the progress risk analysis theory of emotional models and the program evaluation and review technique method. An engineering application showed that the expected construction period increased, and the completion probability decreased considerably with increasing pessimism; the opposite trend occurred as optimism increased. During the process of risk management and control, the prediction model can be used to perform precise quantitative analysis of the expected construction period and completion probability, reduce the blindness of construction management, control decisions of complex giant tunnel projects, and provide a more accurate basis for decision makers to judge risks. The findings of this study can be applied to hydraulic tunnels and can provide a reference for traffic tunnels, railway tunnels, and other similar projects.

Funder

Jiangsu Collaborative Innovation Center for Building Energy Saving and Construct Technology, Young Ph.D. Fund–Funded Projects

Jiangsu Provincial Department of Housing and Urban-Rural Development 2019 Provincial Construction System Science and Technology Project

the 2020 School-level Scientific Research Project of Jiangsu Vocational Institute of Architectural Technology

Publisher

Springer Science and Business Media LLC

Reference30 articles.

1. Xiao, Y. et al. Analysis on schedule risks of diversion tunnel construction based on CSRAM. J. Hydroelectr. Eng. 36, 90–100 (2017).

2. Hu, L., Li, T. & Qiu, W. Study of dynamic prediction and control about tunnel construction schedule and cost. J. Railw. Eng. Soc. 32, 115–121 (2015).

3. Zhang, Y. G., Wang, Y. H. & Wang, M. S. Risk assessment of construction for Bohai Bay subsea tunnel China. Civil Eng. J. 48, 414–418 (2015).

4. Zhuo, B., Gao, X., Jiang, Z. L. & Chen, D. C. Risk assessment of tunnel construction in complexenvironment based on NGBN and FCEM. Constr. Technol. 51, 62–67 (2022).

5. Zhou, X. Tunnel collapse risk warning model based on efficacy coefficient method and geological prediction and its applications. Highw. Eng. 40, 59–63 (2015).

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3