Interconnection Study in Utilizing of Solar Energy for 150 MW Photovoltaic Power Generation through 150 kV Transmission Line

Author:

Halim Levin1

Affiliation:

1. Department of Electrical Engineering, Parahyangan Catholic University, Bandung, Indonesia

Abstract

The interconnection of utility-scale photovoltaic (PV) power plants with the electric grid is a crucial factor that requires comprehensive analysis and assessment. The focus of this research article is on a specific photovoltaic (PV) power plant that is planned for construction in the X Power System located in Indonesia which has 150 MW capacity which has intermittent behavior, experiencing fluctuations in power generation based on the availability of sunlight and the cloud movement. The objective of this paper is to explore the feasibility, technical prerequisites, and potential solutions for the successful integration of the PV power plant into the existing power system. Multiple investigations will be carried out, which is Load Flow, Short-Circuit, and Transient Stability analyses, with the aim of assessing the consequences of linking the PV power plant to the existing power system. Consequently, it is vital to model the X power system conditions prior to the interconnection process. Moreover, modeling an intermittent PV power plant necessitates different approaches compared to conventional power plants. According to the research findings from load flow analysis, the voltage levels near the interconnection point, both prior to and after linking the PV Power Plant, remain within permissible bounds of +5% and -10%. Furthermore, there are no constraints on the load capacity of the transmission lines and Interbus Transformers (IBT) either prior to or following the integration of the PV Power Plant. The short-circuit current around the point of interconnection experiences a marginal increase, and it is advisable to employ circuit breakers (CB) rated at 40 kA for both the PV Power Plant and the switching station. Furthermore, the power system exhibits resilience in preserving its stability, even in scenarios involving abrupt power loss or intermittent generation from the PV Power Plant. These situations can result from unexpected outages or variations in solar radiation. The interconnection of the 150 MW PV Power Plant can be implemented without significant adverse effects on the system's voltage, loading capacity, and stability.

Publisher

FOREX Publication

Subject

Electrical and Electronic Engineering,Engineering (miscellaneous)

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3