Geological and geotechnical evaluation of the tunnel site of the Koto Hydropower Project, Khyber Pakhtunkhwa, Pakistan

Author:

Khan Nasar1ORCID,Siddiqui Muhammad Ejaz2,Ullah Naveed1ORCID,Awais Muhammad3ORCID,Khurshid Salman1

Affiliation:

1. Department of Geology, University of Malakand, Chakdara 18800, Pakistan

2. Sarwar and Company (Pvt.) Limited, Islamabad 45510, Pakistan

3. Department of Geology, University of Swabi, Anbar 23561, Pakistan

Abstract

Hydropower projects provide excellent opportunities to cope with rising energy demands; however, their geological and geotechnical evaluation is fundamental to ensure their long-term performance and stability. Thus, geological and geotechnical investigations were carried out to evaluate the feasibility of a tunnel (7 m diameter and 1880 m length) for the Koto Hydropower Project, Khyber Pakhtunkhwa, Pakistan. Five investigation boreholes with a cumulative depth of 145 m were drilled and samples were collected for qualitative observation and laboratory analyses. The geotechnical investigations include Lugeon and permeability tests to estimate the hydraulic conductivity of the associated rocks. In the boreholes, lithologies and discontinuities such as joints, fractures, veins and shear zones were identified. Lithological logging, rock quality designation and percentage core recovery were used to understand rock behaviour and strength. The rocks encountered are mainly gabbronorites and granodiorites with some amphibolites. The bedrock strength is designated as R4 (strong) with a minor amount of R3 (moderate), indicating suitability and feasibility for tunnel construction. The Main Mantle Thrust is the major tectonic feature, which is located towards the southern side of the study area; however, seismicity along it is not significant. The geological and geotechnical investigation indicated the suitability of the tunnel site for construction.

Publisher

Geological Society of London

Subject

Earth and Planetary Sciences (miscellaneous),Geology,Geotechnical Engineering and Engineering Geology

Reference34 articles.

1. Relationship between hydraulic conductivity of rock and rock quality designation of Itisi multi-purpose dam;Adedokun T.A.;International Journal on Recent and Innovation Trends in Computing and Communication,2016

2. A Review of Hydropower Projects in Nepal

3. Selection of renewable energy technologies for a developing county: A case of Pakistan

4. Geology of Shamozai area in the lower Dir District, NWFP, Pakistan;Asim M.;Journal of Himalayan Earth Sciences,1999

5. Determining rock mass deformability: experience from case histories

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3