Influential factors for risk assessment and allocation on complex design-build infrastructure projects; the Texas experience

Author:

Demetracopoulou Vassiliki,O’Brien William J.,Khwaja Nabeel

Abstract

Introduction: The design-build (DB) delivery method is used to deliver increasingly complex transportation infrastructure projects associated with higher uncertainty. As such, allocating risks in the contract between the owner and design-builder becomes challenging and often leads to higher initial bids, increased contingency, or claims. Learnings from implementation worldwide have underlined the need for improving risk allocation in DB contracts. Most existing studies address risk allocation mechanisms to manage contingency at the contract level. Other studies have recognized the need for owners to adapt their processes to better allocate risks in DB contracts. This study explored the influential factors for risk assessment and allocation for complex DB infrastructure projects, addressing the opportunity to improve transportation owners’ risk allocation processes before the design-builder is selected and the DB contract is awarded.Method: The objectives of this work were achieved by utilizing empirical data collected through 20 interviews with Texas Department of Transportation and private sector experts. The interview data were analyzed using inductive and axial coding. Inductive coding allowed themes to emerge without a pre-existing framework, identifying six influential factors and six pertinent risks on complex DB projects.Results: These factors include the (i) Quality of DB teams, (ii) Level of up-front investigation, (iii) Limitations on the timing of letting, (iv) Design optimization opportunities, (v) Project-specific requirements, and (vi) Relationships with third parties. Through axial coding, the interaction and frequency between the factors and risks were also examined. The coded interactions demonstrated how the identified factors influence allocation for six pertinent risks including right-of-way acquisition, stakeholder approval, site conditions, permits and third-party agreements, railroad interaction, and utility adjustments and coordination. Findings indicate that the evaluation of these interactions can shift the risk allocation from baseline norms established by an agency to correspond to project-specific needs.Contribution: In contributing to the infrastructure project management, this is the first study to examine the factors that influence risk allocation in complex DB projects and examine interactions with pertinent risks, setting the foundation for optimizing allocation based on project-specific needs. In practice, the findings presented in this study can guide owners in adapting their allocation practices, managing, and developing their strategic plan for delivering complex DB projects. The findings can also assist contractors in pricing risks more efficiently and increase competitive bidding.

Publisher

Frontiers Media SA

Reference69 articles.

1. Risk planning and management for the Panama Canal expansion program;Alarcon;J. Constr. Eng. Manage.,2011

2. National cooperative highway research program, transportation research board of the national academies;Anderson,2009

3. The concept of project complexity—a review;Baccarini;Int. J. Proj. Manage.,1996

4. Resilient water and wastewater infrastructure systems through integrated humanitarian-development processes: the case of Lebanon’s protracted refugee crisis;Bakchan;Environ. Sci. Technol.,2021

5. Grasping project complexity in large engineering projects: the TOE (technical, organizational and environmental) framework;Bosch-Rekveldt;Int. J. Proj. Manage.,2011

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3