Evolution Law and Grouting Treatment of Water Inrush in Hydraulic Tunnel Approaching Water-Rich Fault: A Case Study

Author:

Gu Jiheng1,Guo Jiaqi1,Chen Fan1,Li Jianhe2

Affiliation:

1. School of Civil Engineering, Henan Polytechnic University, Jiaozuo 454003, China

2. Changjiang Institute of Survey, Planning, Design and Research, Wuhan 430010, China

Abstract

Tunnel construction adjacent to the fault fracture zone is prone to water inrush disasters, which pose a serious threat to the safety of tunnel construction. To provide theoretical support for the early warning and prevention of water inrush disasters of the tunnel adjacent to the water-rich faults, a numerical analysis based on the three-dimensional discrete element method (DEM) was performed to study the evolution of the displacement and seepage fields of the water-resistant rock mass of a tunnel adjacent to a water-rich fault during the water inrush process by taking the Xianglushan tunnel as the research project. With reference to the obtained results, a grouting reinforcement scheme was developed, and its effectiveness was evaluated. The results indicated that as the tunnel face approached the water-rich fault fracture zone, the effect of water pressure gradually became obvious, and the displacement at the face continuously increased. When the tunnel face was excavated to the position 5 m from the fault, the displacement at the center of the face changed suddenly with a sudden increase in water pressure. The water-resistant rock mass ahead of the center of the face was damaged, and a water inrush disaster occurred in the tunnel. Numerical simulation results demonstrated the feasibility of the grouting reinforcement scheme. The assessment based on the borehole acoustic waves, borehole TV, geological radar detection, and convergence monitoring as well as the excavation results confirmed that the water inrush disasters in the 2# adit of Xianglushan tunnel adjacent to the water-rich fault were effectively prevented and controlled, which can provide a reference for the prevention and treatment of the frequent water inrush disasters in underground projects constructed in the water-rich fault area.

Funder

National Natural Science Foundation of China

Yunnan Province Major Science and Technology Special Plan Project

Publisher

MDPI AG

Reference32 articles.

1. Research progress on key technologies for safe construction and efficient operation of the Dianzhong water diversion project-underground engineering;Zhang;Chin. J. Rock Mech. Eng.,2024

2. Evolution mechanism, monitoring, and early warning method of water inrush in deep-buried long tunnel;Tu;Geofluids,2021

3. Geological investigation and treatment measures against water inrush hazard in karst tunnels: A case study in Guiyang, southwest China;Liu;Tunn. Undergr. Space Technol.,2022

4. Three-dimensional upper bound limit analysis on the collapse of shallow soil tunnels considering root stratification and pore water pressure;Wang;Math. Probl. Eng.,2019

5. A tunnel face failure mechanism for layered ground, considering the possibility of partial collapse;Senent;Tunn. Undergr. Space Technol.,2015

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3