Assessment and Commissioning of Electrical Substation Grid Testbed with a Real-Time Simulator and Protective Relays/Power Meters in the Loop

Author:

Piesciorovsky Emilio C.1,Borges Hink Raymond1,Werth Aaron2,Hahn Gary1,Lee Annabelle3,Polsky Yarom4

Affiliation:

1. Oak Ridge National Laboratory, Electrification and Energy Infrastructures Division, Oak Ridge, TN 37831, USA

2. Oak Ridge National Laboratory, Cyber Resilience and Intelligence Division, Oak Ridge, TN 37831, USA

3. Nevermore Security LLC, 31256 Stone Canyon Rd, Evergreen, CO 80439, USA

4. Oak Ridge National Laboratory, Manufacturing Science Division, One Bethel Valley Rd, Oak Ridge, TN 37830, USA

Abstract

Electrical utility substations are wired with intelligent electronic devices (IEDs), such as protective relays, power meters, and communication switches. Substation engineers commission these IEDs to assess the appropriate measurements for monitoring, control, power system protection, and communication applications. Like real electrical utility substations, complex electrical substation grid testbeds (ESGTs) need to be assessed for measuring current and voltage signals in monitoring, power system protection, control (synchro check), and communication applications that are limited by small-measurement percentage errors. In the process of setting an ESGT with real-time simulators and IEDs in the loop, protective relays, power meters, and communication devices must be commissioned before running experiments. In this study, an ESGT with IEDs and distributed ledger technology was developed. The ESGT with a real-time simulator and IEDs in the loop was satisfactorily assessed and commissioned. The commissioning and problem-solving tasks of the testbed are described to define a method with flowcharts to assess possible troubleshooting in ESGTs. This method was based on comparing the simulations versus IED measurements for the phase current and voltage magnitudes, three-phase phasor diagrams, breaker states, protective relay times with selectivity coordination at electrical faults, communication data points, and time-stamp sources.

Publisher

MDPI AG

Subject

Energy (miscellaneous),Energy Engineering and Power Technology,Renewable Energy, Sustainability and the Environment,Electrical and Electronic Engineering,Control and Optimization,Engineering (miscellaneous),Building and Construction

Reference39 articles.

1. Atwa, O.S.E. (2019). Practical Power System and Protective Relays Commissioning, Academic Press.

2. (2009). IEEE Guide for Power System Protection Testing (Standard No. C37.233-2009).

3. (2023, May 17). Understanding the Commissioning Process for Utility Systems. ComRent Load Bank Solutions. Available online: https://www.tdworld.com/resources/white-papers/whitepaper/20969596/understanding-the-commissioning-process-for-utility-systems.

4. (2020). IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Energy Resources with Electric Power Systems and Associated Interfaces (Standard No. 1547.1-2020).

5. A Novel Whole-View Test Approach for Onsite Commissioning in Smart Substation;Jing;IEEE Trans. Power Deliv.,2013

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3