Locating Potential Run-of-River Hydropower Sites by Developing Novel Parsimonious Multi-Dimensional Moving Window (PMMW) Algorithm with Digital Elevation Models

Author:

Bhagwat Ninad1ORCID,Zhou Xiaobing1ORCID

Affiliation:

1. Department of Geological Engineering, Montana Technological University, Butte, MT 59701, USA

Abstract

We developed a Parsimonious Multi-dimensional Moving Window (PMMW) algorithm that only requires Digital Elevation Model (DEM) data of a watershed to efficiently locate potentially optimal hydropower sites. The methodology requires only open source DEM data; therefore, it can be used even in remotest watersheds of the world where in situ measurements are scarce or not available at all. We used three parameters in this algorithm, and tested the method using the Advanced Spaceborne Thermal Emission and Reflection Radiometer (ASTER) and the Shuttle Radar Topography Mission (SRTM) derived DEMs. Our case study on the Morony Watershed, Montana, USA shows that (1) along with 6 out of the 7 existing hydropower plants being successfully located, 12 new potential hydropower sites were also identified, using a clearance of 1 km, diversion of 90 m, and Hydropower Index (HI) threshold of 109 m as the criteria. For the 12 new potential hydropower sites, 737.86 Megawatts (MW) ± 84.56 MW untapped hydropower potential in the Morony Watershed was also derived; (2) SRTM DEM is more suitable for determining the potential hydropower sites; (3) although the ASTER and SRTM DEMs provide elevation data with high accuracy, micro-scale elevation differences between them at some locations may have a profound impact on the HI.

Funder

National Aeronautics and Space Administration

Publisher

MDPI AG

Subject

Energy (miscellaneous),Energy Engineering and Power Technology,Renewable Energy, Sustainability and the Environment,Electrical and Electronic Engineering,Control and Optimization,Engineering (miscellaneous),Building and Construction

Reference57 articles.

1. Analysis for cost estimation of low head run-of-river small hydropower schemes;Singal;Energy Sustain. Dev.,2010

2. Modelling of hydropower reservoir variables for energy generation: Neural network approach;Abdulkadir;Ethiop. J. Environ. Stud. Manag.,2013

3. A toolbox for the optimal design of run-of-river hydropower plants;Yildiz;Environ. Model. Softw.,2019

4. Flow regime aspects in determining environmental flows and maximising energy production at run-of-river hydropower plants;Kuriqi;Appl. Energy,2019

5. Vytvytskyi, L., and Lie, B. (2019). OpenHPL for Modelling the Trollheim Hydropower Plant. Energies, 12.

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3