In engineering projects, project duration and a cost increase occur in every phase and will propagate their impacts downstream. Associated with the compensation of project duration, the duration and cost impacts are transferred among phases. In this paper, after illustrating the transmission of project duration and cost impacts, we will use the risk transmission theory and GERT (Graphic Evaluation and Review Technique) network technique to build a transmission model. We have designed equivalent parameters of project duration and cost impacts in the GERT model for serial, parallel, and hybrid structures. The algorithm of the GERT network for project cost and duration transmission is analyzed. The effectiveness of this model and algorithm is proved by numerical examples. This paper provides a new analytical method for cost and duration control of engineering projects.
Funder
The Transmission of Project Duration gain-loss and Cost Loss based on the GERT Network Technique
Subject
Physics and Astronomy (miscellaneous),General Mathematics,Chemistry (miscellaneous),Computer Science (miscellaneous)
Reference24 articles.
1. Research on the risk element transmission analytic model of construction network planning project;Li;Chin. J. Manag. Sci.,2007
2. Research on Analytic Model of Project Chain Risk Elements Transmission Based on Risk Ranking Method and Data Mining
3. A supervised manifold learning method
4. Enterprise projects set risk element transmission chaotic genetic model;Li;Res. J. Appl. Sci. Eng. Technol.,2012
5. Risk Element Transmission Model of Construction Project Chain Based on System Dynamic
Cited by
7 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献