A Geotechnical Perspective on a Complex Geological Environment in a High-Speed Railway Tunnel Excavation (A Case Study from Türkiye)

Author:

Gokceoglu CandanORCID,Aygar Ebu Bekir,Nefeslioglu Hakan A.ORCID,Karahan Servet,Gullu Suat

Abstract

The T26 tunnel was designed within the scope of the Ankara-Istanbul high-speed railway in accordance with the speed of 250 km/h. Some serious problems and excessive deformations were encountered during the excavation works. The deformations in the tunnel caused subsidence on the surface and the Tunnel Boring Machine (TBM) became stuck; therefore, tunnel excavation works were suspended. Design works for re-excavation in the T26 tunnel and extracting of the TBM were carried out and the tunnel was re-designed by the New Austrian Tunneling Method (NATM) system. The main purposes of the present study are to describe the problems encountered during the T26 tunnel and to discuss the sources of the problems. The advantages and disadvantages of TBM and NATM methods for the tunnel having difficult ground conditions were discussed. Critical points needing to be considered for the tunnels excavated with TBM through weak ground conditions and the effect of the TBM selection process were discussed. Considering the complex geological and geotechnical structure of the tunnel route, it is possible to say that the T26 case is an interesting case for tunnel engineering. Along the tunnel route, landslides, high seismic activity, groundwater conditions, and extremely weak rock mass features coexist. Therefore, the tunnel route is a very complex environment. However, due to the geometric limitations of the high-speed railways, relocation of the route is not possible. The experiences gained from tunnel excavations under difficult conditions are capable of bringing new horizons to future tunneling studies.

Publisher

MDPI AG

Subject

Computer Science Applications,Geotechnical Engineering and Engineering Geology,General Materials Science,Building and Construction,Civil and Structural Engineering

Reference57 articles.

1. Barton, N. (2009). TBM Prognoses in Hard Rock with Faults Using QTBM Methods, IoM3 Institute of Materials, Minerals & Mining.

2. Barton, N. (2000). TBM Tunnelling in Jointed and Faulted Rock, Balkema.

3. Landrin, H., Blucekert, C., Perrin, J.P., Stacey, S., and Stolfa, A. (2006). ALOP/DSU Coverage for Tunneling Risks?, International Association of Engineering Insurers.

4. A case history of Tunnel Boring Machine jamming in an inter-layer shear zone at the Yellow River Diversion Project in China;Eng. Geol.,2003

5. Effect of adverse geological condition on TBM operation in Ghomroud tunnel conveyance project;Tunn. Undergr. Space Technol.,2009

Cited by 1 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. Modeling of Tunnel Boring Machine Performance Employing Random Forest Algorithm;Geotechnical and Geological Engineering;2023-06-20

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3