BIM Impact on Construction Project Time Using System Dynamics in Saudi Arabia’s Construction

Author:

Alnaser Aljawharah A.1,Alsanabani Naif M.2,Al-Gahtani Khalid S.2ORCID

Affiliation:

1. Department of Architecture and Building Science, College of Architecture and Planning, King Saud University, Riyadh 11574, Saudi Arabia

2. Department of Civil Engineering, King Saud University, P.O. Box 2454, Riyadh 11421, Saudi Arabia

Abstract

Construction delays are a prevalent issue worldwide, and Saudi Arabia is just a short distance from this experience. Although the Saudi construction industry was booming due to Vision 2030, major delays were recorded in numerous construction projects, resulting in extra costs and schedule overruns. Studies on Building Information Modeling (BIM) have increased recently due to their crucial role in managing construction projects. However, more efforts need to be made to define the impact value of adopting BIM using advanced techniques such as System Dynamics (SD). It also aims to demonstrate the BIM impacts globally to encourage taking advantage of such a system. Limited papers studied BIM impact in-depth using advanced techniques such as SD. Thus, A questionnaire was distributed to fifty-nine experts to measure the extent of BIM’s influence on the ten factors affecting project delay times discovered in the literature. The statistical analysis results were used to calculate each factor’s relative importance index (RII), compare them to the results obtained without BIM use, and calculate the relative difference for each factor. These relative differences were considered in the modified SD. The modified SD was applied to a case study representing an academic building in the King Saud University campus. The main finding revealed that BIM decreased construction project delays by 14.55%. In addition, this study found that BIM has a maximum influence on poor site management and supervision by contractors, with a reduction percentage of 17.65%, and a minimum influence on lack of contractor experience and managerial skills, with 11.76%. The SD analysis results confirmed that BIM has a significant impact on reducing construction project delays.

Funder

Ministry of Education

Publisher

MDPI AG

Subject

Building and Construction,Civil and Structural Engineering,Architecture

Reference60 articles.

1. A Review on Significant Factors Causing Delays in Saudi Arabia Construction Projects;Alajmi;Smart Cities,2022

2. Using PIPS to minimize causes of delay in Saudi Arabian construction projects: University case study;Alzara;Procedia Eng.,2016

3. Causes of delay in Saudi public construction projects;Alsuliman;Alex. Eng. J.,2019

4. MOE Ministry of Education (2023, May 28). Kingdom of Saudi Arabia, Available online: https://www.moe.gov.sa/ar/mediacenter/MOEnews/Pages/pr-1442-452.aspx.

5. Saudi Contractors Authority (2023, April 04). COVID-19 Impact on the Contracting Sector in Saudi Arabia Building Resilience in a Turbulent Environment. Available online: sca.sa/16052020091859.pdf.

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3